Users Manual

6. Equipment Commissioning
60
WiBAS-Connect TS, Continued
Procedure for WiBAS-Connect TS with Panel Antenna, continued
Step Action
3 Perform fine alignment, as follows:
Use the spanner key to loosen the azimuth adjustment bolts (A). Perform azimuth
adjustment by moving very slowly the whole system (within the ±10
o
range around
the azimuth axis)
until the voltage readout reaches a desired level.
Use the spanner key to loosen the elevation adjustment bolts (E). Perform
elevation adjustment by moving very slowly the whole system (within the ±10
o
range around the elevation axis) until the voltage readout reaches a desired value.
(A) = Azimuth bolts x 2 (up and down)
(E) = Elevation bolts x 2 (left and right).
The RSSI voltage (actually the voltmeter value) provides a direct
relationship with RSL.
For WiBAS-OSDR see
WiBAS-OSDR terminal station RSSI measurement
calculation formula on page 41,
For WiBAS-Connect see
WiBAS-Connect terminal station RSSI
measurement calculation formula on page 41).
4 Use the adjustable torque wrench for pre-tightening. The final tightening torque
will be applied after alignment process completion.
Continued on next page