User's Manual

StreetNode 6250 PTP with Embedded Node Manager
WebUI Commissioning Manual Edition 1.1
9
Startup & Commissioning Procedure, Continued
Overview
The commissioning of a StreetNode
TM
6250 PTP unit will be carried as follows:
Step
Action
Details Refer to
1
Visit site A. Install StreetNode
TM
6250 PTP, point it
coarsely toward site B and power it up.
StreetNode
TM
6250 PTP
Installation & Cabling Manual.
2
Configure
management.
In case the (default) VLAN with id=1 is
to be used, then set:
Acceptable Frame Type = Tagged
and Untagged (modem configuration).
If a different VLAN is to be used, no
such action is required.
Node Manager for
StreetNode
TM
6250 PTP
Reference Manual, Chapters
4 & 5:
§ Configuring the Inband
Management.
§ Adding VLANs / VLAN
Ports.
§ Configuring Bridge.
3
Configure
StreetNode
operation.
a.
Set site information.
§ Adding Site Information.
b.
Configure the modem operation.
Set the following:
Min Auto PHY Mode = 4QAM
Max Auto PHY Mode = 4QAM
Adaptive Mode = Auto-Manual
Power
§ Configuring the Modem.
c.
Configure the radio parameters.
Set the Tx frequency and Tx power as
provided by the radio planning. Ensure
that Mute = OFF.
§ Configuring the Radio.
d.
Configure bridge.
Use the input provided by the
responsible network operation team.
§ Configuring Bridge.
e.
Save node configuration. § Saving Configuration.
Continued on next page