Installation Guide
10 
STEP 1: PREPARE FRONT FASCIA 
Components Needed 
  Front fascia rails (D) 
  Front fascia splice insert (B)* 
  Fascia dams (foam) 
  Sealant tube & gun 
Tools Recommended 
FIRST: Inter-connect by inserting the hanging 
channel into the front fascia parallel and 
evenly on a flat level non-abrasive surface or 
slab. Make sure both front fascia and hanging 
channel rails remain even and flush together 
by taping every 15” across span. 
DO NOT USE PERMANENT MARKER 
SECOND:  Mark top of front fascia & hanging 
channel every 12” from end to end with a 
small pen/marker/pencil.  
NOTE: Last space will be 12 ¾” opening to 
allow for flange width on last panel. 
DO NOT cut the hanging channel. 
THIRD:  12” marks will be needed during 
future STEPS for locking-in roof panels in the 
correct location to ensure water-tight 
connection. 
DO NOT cut the hanging channel. 