21. COMMISSIONING REPORT
This heater has been factory fired and tested prior to shipment. However, it is not a Plug-in
appliance. Commissioning and field adjustment to correct settings is required.
COMPLETE THIS COMMISSIONING REPORT AND
FILE THIS MANUAL AT SITE FOR FUTURE REFERENCE
INSTRUCT THE END USER THAT THIS MANUAL MUST BE KEPT SECURE
A QUALIFIED SERVICE TECHNICIAN CALLING FOR TECHNICAL SUPPORT
MUST PROVIDE THE INFORMATION FROM THE
COMPLETED COMMISSIONING REPORT
TECHNICAL SUPPORT: 1-877-446-3727
BUSINESS HOURS: 8:30 a.m. to 5:00 p.m. Eastern time
Technical commissioning report continues next page ….
COMMISSIONING REPORT
AS PER I&O MANUAL AND LOCAL/NATIONAL CODES
CONTRACTOR:
STREET:
CITY:
STATE/PROV:
ZIP:
PHONE:
CELL:
JOBE NAME:
CITY:
STATE/PROV:
HEATER MODEL NUMBER :
HEATER SERIAL NUMBER :
Located on burner rating plate
Located on burner rating plate