Installation Sheet

8
12. ONLY FOR S-TIFAS 65 INSTALL:
Spread a layer of mortar into the Tile
Insert Frame (TA65), allowing for thinset
and material to finish 1/16” above the
metal frame. Allow to dry, spread thinset
and finishing material.
12. SOLO PARA S-TIFAS 65 INSTALACION:
Extender una capa de mortero en Tile
Insert Frame (TA65), permitiendo el thinset
y material que termine 1/16” arriba del
marco de metal. Permita que se seque,
extienda thinset y material terminado.
11. Using desired material, mark the thickness
along the channel so that it will nish 1/16”
above the channel. Lay nal mortar bed
across the wet area. Pitch this bed in one
plane toward the linear drain. Allow space for
thinset and nishing material to nish 1/16”
above the channel. After dry, apply a bead of
silicone caulk around the channel. Lay thinset
and nishing material to the edge of the
combined stainless steel channel. DO NOT
allow material to nish on the stainless steel
channel edge. (Please refer to gures below)
11. Usando el material que desea, marque
el espesor a lo largo del canal de modo que
termine 1/16” arriba del canal. Coloque mortero
denitivo través de la zona húmeda. Brea esto
en un plano hacia el drenaje lineal. Permita el
espacio para el thinset y material terminado
1/16” arriba del canal. Después que este
seco, aplique una gota de masilla de silicona
alrededor del canal. Colocar thinset y material
hasta el borde del canal de acero. NO PERMITA
el material que termine en el borde del canal de
acero. (Por favor referirse a las cifras inferiores)
Waterproong Membrane
Stainless Steel
Channel Assembly
Final Mortar Bed
Threaded Outlet
Pre-Pitched Mortar Bed
Suboor
Finishing Material
Backer Board
Caulking
Mortar Bed
Mortar Bed
Sub-oor
Waterproong
Membrane
Finishing Material
Assure that grate is lower
than installed tile
Mortar Bed
Mortar Bed
Sub-oor
Waterproong
Membrane
Before nishing
material
Antes que el material
esté terminado
After nishing
material
Desps que el material
esté terminado