User's Manual

Table Of Contents
DIB-500 R4.1 Component replacement
Replacing components of the VAC and alarm system expansion – optional
196 Installation, Operation and Service Manual 90DIB500R41IM_FCC02 99.1
Risk of damage
Damage of installed components. If you apply excessive force when tightening the
mounting screw, installed components of the equipment rack may be damaged.
Use a size 2 torque cross-head screwdriver for tightening the fastening screw.
Ensure that the maximum torque does not exceed the following value: 1.5 Nm.
4. Tighten the mounting screw on the mounting frame.
The connector of the rectifier module is connected to the mounting frame.
5. Take the network element back to operation to test the function of the rectifier mod-
ule, refer to section 9.1 on page 167.
The rectifier module starts automatically.
The SC200 detects the rectifier module and loads the required configuration
parameters.
LED Indicator of the rectifier module
The status of the rectifier module is indicated via the LEDs on the front after the initiali-
sation of the SC200. During the initialisation (approx. 90 seconds) the "Power" LED will
light up and the "Minor" LED will flash.
6. Ensure that the "Power" LED (3) is lit and the "Major Alarm" (1) and "Minor Alarm"
(2) LEDs are off, refer to Figure 11.15.
Figure 11.15 Front view of the rectifier module – indicators (LEDs)
7. Perform the concluding tasks, refer to Table 11.24 on page 193.
You have successfully installed the rectifier module.
11.8.2 Replacing the mounting frame and the SC200
Depending on the voltage supply and the optional components, the mounting frame
may have different constituents, refer to Table 3.7 on page 37.
The mounting frame is fastened with two retaining brackets that are secured to the
equipment rack on the front with four mounting screws.
3
1
2