User's Manual

Table Of Contents
DIB-500 R4.1 Recommissioning
Recommissioning after a permanent service interruption
168 Installation, Operation and Service Manual 90DIB500R41IM_FCC02 99.1
9.2 Recommissioning after a permanent service interrup-
tion
The present section describes the proper procedure for recommissioning after a perma-
nent shutdown of the product. For this purpose, the disconnected physical connections
must be restored.
Proceed as follows to recommission a network element after a permanent shutdown:
Preparation:
The equipment rack must be connected to the grounding system.
The component rack must be connected to the voltage supply.
The voltage supply must be switched off.
Carry out the following steps:
1. Connect the antennas, refer to section 5.15 on page 129.
2. Connect the required cables, refer to section 5.6 on page 107 and section 5.7 on
page 113.
3. Switch on the voltage source, see section 5.14 on page 129.
4. Switch on the DIB-500 R4.1, see section 5.15 on page 129.
You have successfully recommissioned a network element.