User's Manual
Table Of Contents
- 1 Notes on the document
- 2 Safety regulations
- 3 Product description
- 3.1 Constituents
- 3.1.1 Voltage supply and alarming system
- 3.1.1.1 Terminal block
- 3.1.1.2 Expansion for VAC voltage supply (VAC voltage supply unit)
- 3.1.1.3 Alarm system expansion
- 3.1.1.4 SC200 - optional (VAC or alarm system expansion)
- 3.1.1.5 Alarm input/output module - optional (VAC or alarm system expansion)
- 3.1.1.6 Rectifier module - optional (VAC expansion)
- 3.1.2 E1 connection board
- 3.1.3 Redundancy package with LAN Routing Unit (LRU)
- 3.1.4 On/off switch
- 3.1.5 TIB transceiver module (TETRA Indoor Base)
- 3.1.6 Antenna Coupling System (ACS)
- 3.1.7 Fan unit
- 3.1.8 Cavity coupler (only for the Cavity variant)
- 3.1.9 Redundancy options for the DIB-500 R4.1 or the Base Station Function (BSF)
- 3.1.1 Voltage supply and alarming system
- 3.2 Interfaces
- 3.3 Wiring diagrams
- 3.4 Scope of delivery
- 3.1 Constituents
- 4 Transport and storage
- 5 Setup and commissioning
- 5.1 Safety measures and prerequisites
- 5.2 Tools, aids and materials
- 5.3 Installing equipment racks
- 5.4 Removing the top cover of the mounting frame
- 5.5 Connecting equipment racks (as of 5 carriers)
- 5.6 Connection to the electrical system
- 5.7 Connecting Ethernet cables
- 5.8 Installing the GPS antenna
- 5.9 Installing the GPS protector - optional
- 5.10 Connecting antennas
- 5.11 Connecting external alarm sensors (LSA+)
- 5.12 Connecting external alarms - optional, with VAC or alerting expansion
- 5.13 Mounting the top cover of the equipment rack
- 5.14 Switching on the voltage source
- 5.15 Switching on the DIB-500 R4.1
- 6 Configuration
- 6.1 Configuring the software
- 6.1.1 Work equipment
- 6.1.2 Preparatory measures
- 6.1.3 Deleting the ARP buffer
- 6.1.4 Configuring and generating network configurations via the NMC-515 ConfigurationManager
- 6.1.5 Creating the download repository
- 6.1.6 Adapting IP addresses (with more than one transceiver module)
- 6.1.7 Performing an initial download via NMC-522 DownloadManager
- 6.2 Adjusting a cavity coupler - optional (cavity variant only)
- 6.3 Concluding tasks
- 6.1 Configuring the software
- 7 Function tests and operating surveillance
- 8 Service interruption
- 9 Recommissioning
- 10 Maintenance
- 11 Component replacement
- 11.1 Safety measures and prerequisites
- 11.2 Overview of replacement components and tools, aids and materials
- 11.2.1 Replacing the TIB transceiver module (tools and aids)
- 11.2.2 Replacing the ACS (tools and aids)
- 11.2.3 Replacing components of the fan unit (tools, aids and materials)
- 11.2.4 Replacing the LRU (tools and aids)
- 11.2.5 Replacing the top hat rail power supply unit (tools and aids)
- 11.2.6 Replacing components of the mounting frame/the voltage supply unit (tools, aids and materials)
- 11.2.7 Replacing cavity couplers (tools and aids)
- 11.2.8 Replacing the GPS protector (tools and aids)
- 11.3 Replacing the TIB
- 11.4 Replacing the ACS
- 11.5 Replacing fan unit constituents
- 11.6 Replacing the LRU - optional (redundancy package)
- 11.7 Replacing the top hat rail - optional (redundancy package)
- 11.8 Replacing components of the VAC and alarm system expansion - optional
- 11.9 Replacing cavity couplers - optional (cavity variants only)
- 11.10 Replacing the GPS protector - optional
DIB-500 R4.1 Setup and commissioning
Removing the top cover of the mounting frame
94 Installation, Operation and Service Manual 90DIB500R41IM_FCC02 – 99.1
5.4 Removing the top cover of the mounting frame
To perform work in the equipment rack, the top cover of the equipment rack has to be
removed.
Removing the transportation lock – optional, only for VAC or alarm system
expansion
Upon delivery, a transportation lock is installed between the mounting frame and the
upper cover of the equipment rack, retained by the upper cover of the equipment rack.
This transportation lock must be removed prior to/while commissioning the product.
The transport lock can be removed after the upper cover of the equipment rack has
been removed. Keep the transport lock in a safe place, you may need it again for trans-
ports later on.
Proceed as follows to remove the top cover:
Preparation:
✓ The tools, auxiliary means and materials specified must be available, refer to
section 5.2 on page 90.
Carry out the following steps:
Keeping materials
Keep all the materials such as fastening screws in a safe place. You will need them
again.
1. Loosen the mounting screws of the grommet using a size 2 cross-head screw-
driver, refer to Figure 5.2.
Figure 5.2 Top equipment rack cover – grommet mounting screws