Step
➊
Step
➋
Step
➌
Step
➍
Low Water Cut-Off
For Residential
Hot Water Boilers
24 VAC Operating Voltage
Model 1100
Determine Mounting Location
The Safgard 1100 must be installed at or above the
minimum safe water level established by the boiler
manufacturer. The 1100 can be installed directly into
the boiler if a suitable tapping is available
. The
1100 can also be installed in the boiler piping using a
standard 3/4" tee
.
Note: When installing in piping, select a location
close to the boiler to ensure the 4' wiring harness will
reach the 24-Volt transformer. The cut-off should be
installed on the boiler side of the circulator or shut-off
valves.
IMPORTANT: Check for adequate clearance
(minimum 1/4") from metal probe sensor to any
surface inside the boiler or pipe.
Do not install in a location that could hold or trap
water in the event of a low water condition.
Apply Teflon
®
tape to the
threads of the
Model 1100. Do
not use pipe
dope or other
pipe sealants.
Hand tighten
the control into
boiler tapping
or pipe tee. Be
careful not to
cross thread.
Note: Do not
use a wrench.
Hand tighten
only.
Plug wire
harness into
connector on
face of control.
WARNING: To prevent electrical shock or equipment damage, power must be off during installation or servicing of the control. To pre-
vent serious burns, the boiler should be thoroughly cooled before installing or servicing control. Only qualified personnel may install or
service the control in accordance with local codes and ordinances. Read instructions completely before proceeding.
Model 1100 Instructions 8/13/03 2:52 PM Page 3