Install Instructions
• Programmable Feed Delay Settings: Prevents over filling by
allowing time for condensate to return to the boiler before initiating a
feed cycle.
• Programmable Feed Amount Settings: Includes one setting to raise
the water level to the boiler control and five additional settings to raise
the water level above the boiler control.
• LED Status Indicator: Displays mode of operation. Also provides
timer for convenient set-up of programmable feed amount setting.
• Manual Feed Button: Allows for manual feeds with the touch of a
button.
• Lock-Out Flood Protection: Locks out after sustained 10 minute feed
cycle to prevent flooding.
• Water Meter: Heavy duty meter tracks make-up water added to
system. (Not included with Model VXTC-WF).
MODEL VXTC
Programmable
Water Feeder for
Commercial Boilers
120 VAC Operating Voltage
COMMERCIAL
A
B
C
D
D
E
F
VXTC COMPONENTS
A 3/4" NPT “Y” strainer
B 10 GPM flow restrictor
C 3/4" NPT solenoid valve
D (2) 3/4" NPT brass adapters with
connection gaskets
E Heavy-duty water meter
F VXTC controller
Be sure flow arrows on solenoid, meter
and strainer are aligned correctly. Use
teflon tape between meter and solenoid
to prevent leakage.
INSTALLATION
WARNING
Frozen pipes/water damage. Central heating systems are prone to shut down as a result of power or fuel outages,
safety related fault conditions or equipment failure. Installation of freeze protection monitoring or other precautions is recom-
mended for unattended dwellings in climates subject to sustain below-freezing temperatures.
WARNING
Electrical shock hazard. To prevent electrical shock, dea th or equipment damage, disconnect power supply before installing
or servicing control. Only qualified personnel may install or service this control in accordance with local codes and ordinances.
Read instructions completely before proceeding.
Prior to piping, remove the solenoid
valve from the VXTC control housing.
The VXTC is designed for the installation in 3/4" NPT black iron or steel piping. For servicing of the
control, the VXTC should be installed with unions and a bypass. The bypass should be construct-
ed so that all water added to the boiler is metered.