Installation Manual

1027144–0001 Draft – Revision D.01
Installation summary 1–3
RT installation
Components to be installed
The following AIReach Broadband components are installed at the
RT site:
ODU(s) – Integrated antenna and transceiver
IFL
Indoor unit(s) (IDU), including:
- IDU channel and control module (CCM)
- IDU service–specific interfaces (SSIs)
Summary of installation steps
RT installation consists of the following main tasks:
Ground the rack (if a rack is used) – page 3–2
Install IDU chassis – page 3–3
Ground the IDU chassis – page 3–12 (ac) or 3–15 (dc)
Connect power to power supply – page 3–13 (ac) or 3–15 (dc)
Install CCM – page 3–24
CCM power–on test – page 3–26
Install SSIs – page 3–28
Install expansion IDUs (EIDUs) (if used) – page 3–34
Determine IFL cable route – page 4–6
Install the IFL cable (inside the building) – page 4–9
Install IFL lightning arrestor – page 4–10
Ground the lightning arrestor– page 4–13
Install the IFL cable (on the roof) – page 4–14
Test the IFL cable – page 4–16
1.2
Installation
summary and
checklist