Commissioning the RT 7–23
RT installation
This test verifies the fractional DS3 connection from the HT to the
RT.
Requirements
The fractional DS3 test described below requires the following:
The RT must be fully installed, commissioned, and in
contact with the EMS through the hub.
The HT must be operational and in contact with the EMS.
Fractional DS3/DS1 services must be configured and
provisioned.
There must be no alarms present at the RT location.
A loopback connector must be connected at the HT, either
at the input/out port connector of the HT DS3 SSI or at the
DS3 patch panel. (Refer to figure 7-8.)
Test procedure
1. Connect a DS3 test set to the out/input connector on the RT
DS3 SSI.
2. Select:
- C bit framing
- Recovered clock
- DS3 interface
Fractional DS1 services may be dropped from the DS3 data
stream and tested using QRSS test pattern.
3. Run the test for 1 hour.
Results
The RT passes if there are no errors and no clock or frame slips
during the test.
Record the results on the form on the following page (or make a
photocopy).
Fractional DS3 test