1027144–0001 Draft – Revision D.01 7–2 Commissioning the RT
RT installation
To ensure successful commissioning, you must verify that the
prerequisites listed below have been accomplished. These tasks
must all be completed prior to commissioning. If any of them has
not been done, make sure they are completed before you proceed
with commissioning.
The RT ODU, IFL, and IDU must be installed and connected.
If you have followed all previous instructions, this
prerequisite is satisfied when you connect the IFL to the
CCM (IDU), as instructed on page 7–4.
The Element Management System (EMS) hardware and
software must be installed and operational.
All physical LAN connections between the RT and EMS
must be completed.
The EMS database must be loaded and operational.
The EMS operator has entered the RT electronic serial
number (ESN) into the EMS database.
The RT ESN is printed on a tag attached to the CCM and can
also be read from the CCM LCD—from the Main Menu ESN
display.
The installer must know the (RT) ODU frequency to be used
and the identification number of the HT the RT will
communicate with. These are provided by network planning
personnel.
The hub and HT must be installed and operational. The HT
must be properly aligned.
CCM must be installed in the IDU as specified in the
configuration documents. (SSIs are not required for
commissioning.)
The RT cannot be located closer than 109 yards (100 meters)
from the HT.
7.1
Prerequisites for
commissioning