10271450001 Revision D 1–4 Installation summary Hub installation
Connect the IFL cable to the ODU – page 5–15
Install the hub rack (optional) – page 6–2
Ground the rack – page 6–6
Install indoor unit (IDU) – page 6–7
Connect power supply – page 6–11
Ground the IDU chassis (if required) page 6–14 (ac) or
6–17 (dc)
Install CCM – page 6–26
Install SSIs – page 6–28
Connect IFL to the CCM – page 6–32
For each IDU, repeat steps on pages 6–7 through 6–32.
Install CCM redundancy bus cable (if backup HT is present)
– page 6–33
Conduct CCM power–on test – page 6–36
Check component status – page 6–39
Verify prerequisites for commissioning – page 7–2
Perform commissioning steps – page 7–3
Test HT to RT connections (if possible) – page 7–8
Weatherproof connections – page 8–2
Obtain customer signoff – page 8–3
For detailed installation instructions, see chapters 2 through 8.