1027144–0001 Revision D 3–2 Installing indoor RT equipment
RT installation
If the RT IDU will be mounted in a rack, the rack must be
grounded, as shown in figure 3-1:
1. Run a ground wire from the rack location to the master
ground bar in the equipment room. This wire must be No. 2
AWG, green, stranded, and shielded.
2. Ground the rack by connecting a No. 6 AWG wire from the
rack to the No. 2 AWG ground wire.
Use a 2–hole lug to connect the No. 6 AWG wire to the
rack. Remove paint and apply anti–oxidant as shown in the
illustration.
T0006050
Top of rack
from rear
Lug connection
close up view
Frame
lug
Remove paint to
bare metal, on
both sides, and
apply anti-oxidant.
Metal rack
HTAP connector
with cover
No. 2 AWG wire
(green) to master
No. 6 AWG wire
Frame
lug
To a subsequent
rack (if present)
Figure 3-1 Rack ground connections
3.1
Rack grounding