User's Manual
Table Of Contents
- Title page
- Contents
- About this manual
- Safety information
- Ch 1 - Installation summary
- Ch 2 - Prerequisites
- Ch 3 - Installing mast mounts
- Ch 4 - Installing ODUs
- Ch 5 - Installing IFL cables
- Ch 6 - Indoor equipment
- Ch 7 - Commissioning HTs
- Ch 8 - Final steps
- Ch 9 - Troubleshooting
- Ch 10 - Maintenance
- App A - Acronyms
- App B - Standards compliance
- App C - Terminating IFL cables
- Index
1027145–0001 Revision E
2–6 Prerequisites
Hub installation
To install AIReach Broadband HT equipment, you will need the
materials listed in table 2-2 . This is a list of key, mostly
specialized materials. It is not a comprehensive list. In addition to
the listed materials, installers should carry materials that are
commonly required to install outdoor telecommunications
equipment.
Table 2-2 Specialized materials required for RT installation
√
Item Purpose (or other comments)
IFL cable For specifications, see page 5–2.
Ground cable IDU, ac (if not grounded through the power
cable): No. 16 AWG, green
IDU, dc: No. 14 AWG, green
ODU and lightning arrestor: No. 6 AWG or
greater, green
For rack installations (rack to ground bar): No. 2
AWG, green, stranded, and shielded
N type connectors N connectors, for IFL cable, see page 5–3.
Concrete blocks Used to anchor mast mount. For details, see
section 3.7 on page 3–6.
Weatherproofing compound Used to seal outdoor IFL connections. See
section 8.1 on page 8–2.
Outdoor waterproof tape Used to seal outdoor IFL connections. See
section 8.1 on page 8–2.
2.4
Specialized
materials