RTN 360 V100 Quick Installation Guide Date: 2014-02-15 Copyright © Huawei Technologies Co., Ltd. 2014. All rights reserved. No part of this document may be reproduced or transmitted in any form or by any means without prior written consent of Huawei Technologies Co., Ltd. Huawei Technologies Co., Ltd. Address: Huawei Industrial Base Bantian, Longgang Shenzhen 518129 People's Republic of China Website: http://www.huawei.com Email: support@huawei.
Safety Precautions Thunderstorms Corrosion Do not work with electrical current or work in elevated or exposed locations during a thunderstorm. Anti-corrosion measures are required if an RTN 360 is installed in a location that is prone to corrosion. Contact the local Huawei office for details. A location is prone to corrosion if it is: Extreme weather conditions •Within 3.7 km of an ocean or a salt water lake RTN 360 is usually installed outdoors.
Installing an RTN 360 Equipment Components A B Appearance and ports D Mounting kits USB flash drive Front view Inside the maintenance compartment 1 2 3 4 RSSI/NMS port • The recommended USB flash drive is a 4 GB Netac U208. If a different model or capacity is required, contact the local Huawei office. USB flash drives not meeting requirements may be incompatible. • The appearance of the shipped USB flash drive may differ from that shown here.
Terminating an Outdoor Network Cable with Shielded RJ45 Connectors Prepare an outdoor network cable and shielded RJ45 connectors. Prepare the following tools. Arrange the core wires according to the pin assignments and cut them neatly (exposing a length of 12 mm). Strip the cable. 8: brown 7: white and brown 6: green 5: white and blue 4: blue 3: white and green 2: orange 1: white and orange RJ45 connector crimping tool Length of the stripped cable: 20 mm Diagonal pliers 1. 2. 3. 4. 5.
Installing an RTN 360 1 Installing an RTN 360 at the Edge of a Mobile Backhaul Network 1 1 Install an RTN 360 on a pole or wall. 2 Install the ground cable. 3 Connect one end of an outdoor network cable to port P&E on the RTN 360. RTN 360 1 Optional: Install the RTN 360 on a pole. PoE supports a maximum distance of 100 meters. Commissioning procedure 4 5 Optional: In this example, port GE(e) is not used. In practice, determine whether to use this port based on your service plan.
Installing an RTN 360 2 Installing RTN 360s at 2x(1+0) Aggregation Sites 2 1 Install two RTN 360s on a pole or wall. 2 Install their respective ground cables. 3 Connect an outdoor network cable to port P&E on each RTN 360. RTN 360 1 Optional: Install the RTN 360 on a pole. PoE supports a maximum distance of 100 meters. Optional: In this example, port GE(e) on neither RTN 360 is used. In practice, determine whether to use this port based on your service plan.
References for Installation Optional: Installing an RTN 360 on a Pole Pass the hose clamps through the fastener and fix the hose clamps on a pole using the screws of the hose clamps. Install the RTN 360 box securely on the fastener. Before fixing the hose clamps, ensure that the azimuth faces the peer site. This side up Unscrew the azimuth adjustment nut. Hook the RTN 360 box (with the attachment plate installed) to the fastener along the dowel. Tighten the azimuth adjustment nut using a hex key.
References for Installation Installing Cables Install a ground cable. Ensure that the OT terminal of the ground cable is correctly installed. Install an outdoor network cable. 1. Unscrew the PG cover installed on port P&E of the RTN 360 using a 1.8 N•m torque wrench (rotating the wrench counterclockwise). 2. Attach a cable tie to the network cable to prevent the PG cover from sliding down. 3/4. Route the network cable through the PG cover and connect the cable to port P&E of the RTN 360. 5/6.
References for Installation Aligning an RTN 360 Install the alignment scope. Holes for installing the alignment scope Eyepiece Adjust the azimuth and elevation of the RTN 360 by rotating the azimuth and elevation adjustment nuts. . Lens By rotating azimuth adjustment nut (nut 1), you can adjust the azimuth of the RTN 360 from -50° to +50°. 1 2 Adjust the azimuth and elevation of the local RTN 360 slowly to move the crosshair of the alignment scope to the peer RTN 360.
References for Installation Powering On an RTN 360 •After unpacking an RTN 360, power it on within 24 hours. •Do not power off an RTN 360 for more than 24 hours during maintenance. •Ensure that the Dock is powered on and works properly. •On an RTN 360, only port P&E supports power over Ethernet. RTN 360 RTN 360 Use clips to fix any indoor sections of the outdoor network cables that connect to ports WAN, LAN0, and LAN1 on the Dock, and remove the plugs in the cable trough.
References for Installation Loading Configuration Data and Measuring the RSL Load configuration data. Measure the RSL. USB flash drive Close the maintenance compartment. Open the maintenance compartment. Web LCT RSL tester If a Wi-Fi module is installed at the USB port, you can determine whether the Wi-Fi module is working properly by enabling it to search for the SSID of an NE in the wireless LAN. If the SSID can be searched out, the Wi-Fi module is working properly.
References for Installation 22/23 >>