Table 1-12 lists the checking items for other cable connections.
Table 1-12 Checklist for other cable connections
No.
Item
1
The connectors of the other cables must securely connected.
2
Labels on the cables are legible and bound based on the engineering
requirements. The cables must be bound tightly and neatly. The
sheaths of the cables must not be damaged.
3
Positions for routing the cables must meet requirements of the
engineering design.
4
There are no connectors or joints on each PGND cable. None of
PGND cables can be short-circuited or reversely connected. In
addition, these cables are not damaged or broken.
5
PGND cables are separately bound from other cables.
6
The protection grounding of the eAN3810A and the surge
protection grounding of the building share one group of ground
conductors.
Power-On Check on the eAN3810A
This section describes the procedure for performing a power-on check on the eAN3810A.
eAN3810A Power-On Check Procedure
After you unpack a eAN3810A, you must power on it within 24 hours. If you power off the
eAN3810A for maintenance, you must restore power to it within 24 hours.