eAN3710A V100R001C00 Hardware Installation Guide Issue 01 Date 2016-12-26 HUAWEI TECHNOLOGIES CO., LTD.
Copyright © Huawei Technologies Co., Ltd. 2016. All rights reserved. No part of this document may be reproduced or transmitted in any form or by any means without prior written consent of Huawei Technologies Co., Ltd. Trademarks and Permissions and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd. All other trademarks and trade names mentioned in this document are the property of their respective holders.
eAN3710A Hardware Installation Guide 1 1 eAN3710A Hardware Description eAN3710A Hardware Description About This Chapter Overview This section describes the exterior, ports, indicators and cables of eAN3710A. Product Version Unless otherwise stated, "eNodeB", "Pico", "eAN", and "AirNode" in this document refer to the 3710 series AirNode. The 3710 series AirNode is a base station that provides communications services in Huawei eLTE-IoT solution.
eAN3710A Hardware Installation Guide 1 eAN3710A Hardware Description 1.3 Mounting Kits This section describes the mounting brackets for installing a eAN3710A. 1.4 Cables This section describes eAN3710A cables. 1.1 eAN3710A Equipment This section describes the exterior, ports and indicators of eAN3710A. 1.1.1 eAN3710A Exterior This section describes the exterior and dimensions of a eAN3710A. Figure 1-1 shows the exteriors of the eAN3710A.
eAN3710A Hardware Installation Guide 1 eAN3710A Hardware Description Figure 1-2 eAN3710A dimensions 1.1.2 eAN3710A Ports This section describes ports on the eAN3710A panels. An eAN3710A has a bottom panel, and cabling cavity panel. Figure 1-3 shows the ports on the eAN3710A panels. Figure 1-3 Ports on the eAN3710A panels Table 1-1 describes ports on the eAN3710A cabling cavity panels. Issue 01 (2016-12-26) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
eAN3710A Hardware Installation Guide 1 eAN3710A Hardware Description Table 1-1 Ports on the eAN3710A cabling cavity panels Port/Slot Description PoE Used for power supply and data transmission. RGPS Used for clock synchronization. Micro SD Used for housing a micro SD card. This slot is used in the case of deployment. Mini USB Used for testing a port. There are four RF ports on an eAN3710A bottom panel, Table 1-2 lists the TX/RX frequency band supported by the RF ports.
eAN3710A Hardware Installation Guide 1 eAN3710A Hardware Description Table 1-3 eAN3710A indicators Indicators Description LINK Link status WIFI Wi-Fi processing unit status RUN Cellular processing unit status ETH ETH status 1.2 Auxiliary Devices The PSE or Dock supplies power to a eAN3710A through an Ethernet cable in PoE mode. 1.2.1 PSE This section describes the appearance, dimensions, ports, and indicators of the PSE, and the PSE specifications.
eAN3710A Hardware Installation Guide 1 eAN3710A Hardware Description Figure 1-6 PSE ports and indicators Table 1-4 describes PSE ports. Table 1-4 PSE ports No. Label Meaning 1 - Power supply port used for PSE power supply 4 DATA Data input port connecting to a transmission device 5 PoE PoE output port connecting to the eAN3710A Table 1-5 describes PSE indicators. Table 1-5 PSE indicators No. Label Status Description 2 AC Steady green The power supply is normal.
eAN3710A Hardware Installation Guide 1 eAN3710A Hardware Description No. Label Status Description normal. Steady off The connection to the eAN3710A is abnormal or the PSE is faulty. Specifications Table 1-6 lists PSE specifications. Table 1-6 PSE specifications Item Specifications Input voltage 90 V AC to 264 V AC Input voltage frequency 47 Hz to 63 Hz Output voltage 56 V DC 1.2.2 Dock The Dock supplies power and transfer transmission to a eAN3710A through an Ethernet cable in PoE mode.
eAN3710A Hardware Installation Guide 1 eAN3710A Hardware Description Figure 1-7 Exterior and dimensions of a Dock Ports The ports are inside the Dock. Figure 1-8 shows the positions of ports on the Dock. Figure 1-8 Ports on the Dock Issue 01 (2016-12-26) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
eAN3710A Hardware Installation Guide 1 eAN3710A Hardware Description Table 1-7 describes ports on the Dock. Table 1-7 Meanings of ports on the Dock Label Description OPT FE/GE optical port, used for connecting an external transmission devices. L/N/PE AC power port, used for connecting an external power supply device. EXT-ALM Environment monitoring port that provides four dry contacts, used for connecting external devices and monitoring alarms.
eAN3710A Hardware Installation Guide 1 eAN3710A Hardware Description Figure 1-9 Positions of external indicators on the Dock Table 1-8 describe indicators on the Dock external indicators. Table 1-8 Dock external indicators Indicator Meaning RUN Operating status ALM Alarm status ACT Service status Table 1-9 describe indicators on the Dock internal indicators.
eAN3710A Hardware Installation Guide 1 eAN3710A Hardware Description 1.3 Mounting Kits This section describes the mounting brackets for installing a eAN3710A. 1.3.1 eAN3710A Mounting Kits This section describes mounting kits and attachment plates for installing eAN3710A. Figure 1-10 shows a mounting bracket and a attachment plate. Figure 1-10 Mounting bracket and common attachment plate for eAN3710A (1) Attachment plate (2) Mounting bracket (3) Hose clamp (4) Expansion bolt 1.3.
eAN3710A Hardware Installation Guide 1 eAN3710A Hardware Description Figure 1-11 Appearance of a separate Dock mounting bracket (1) Hole for routing a hose clamp (2) Ground terminal (3) Hole for a captive screw (4) Hole for inserting an expansion bolt 1.4 Cables This section describes eAN3710A cables. 1.4.1 Cable List This section describes eAN3710A cable connections. Table 1-10 lists eAN3710A cables. Table 1-10 List of eAN3710A cables Cable 1.4.
eAN3710A Hardware Installation Guide Cable 1 eAN3710A Hardware Description One End Connector The Other End Connected to ... Connector Connected to ... Dock/LAN0 port 1.4.3 PGND cable OT terminal (M6) Ground terminal on the eAN3710A OT terminal (M8) Ground terminal on the ground bar OT terminal (M6) Ground terminal on the Dock OT terminal (M8) Ground terminal on the ground bar 1.4.
eAN3710A Hardware Installation Guide 1 eAN3710A Hardware Description Table 1-11 shows the pin assignment for wires of the Ethernet cable. Table 1-11 Pin assignment for wires of the Ethernet cable Pin of the RJ45 Connector Color Core Wire Pin of the RJ45 Connector X1.2 Orange X2.2 X1.1 White/Orange Twisted pair cable X1.6 Green X2.6 X1.3 White/green Twisted pair cable X1.4 Blue X2.4 X1.5 White/Blue Twisted pair cable X1.8 Brown X2.8 X1.7 White/brown Twisted pair cable X2.1 X2.
eAN3710A Hardware Installation Guide 1 eAN3710A Hardware Description Installation Position The M6 OT terminal of the PGND cable is connected to the ground screw on the eAN3710A and Dock, and the M8 OT terminal of the PGND cable is connected to the ground bar at the site. 1.4.4 RF Jumper The eAN3710A RF jumper transmits and receives RF signals. If the customer prepares the RF jumper, the length of the RF jumper should be as short as possible and not exceed 2 m (6.56 ft.).
eAN3710A Hardware Installation Guide 2 2 eAN3710A Hardware Installation Guide eAN3710A Hardware Installation Guide About This Chapter Overview This document describes the process of installing eAN3710A. Product Version Unless otherwise stated, "eNodeB", "Pico", "eAN", and "AirNode" in this document refer to the 3710 series AirNode. The 3710 series AirNode is a base station that provides communications services in Huawei eLTE-IoT solution.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide This section describes how to unpack and check the delivered equipment to ensure that all the materials are included and intact. 2.4 Installation Process This section describes the eAN3710A installation process. 2.5 Obtaining the ESN Before installing the eAN3710A, record its electronic serial number (ESN) for future use during commissioning. 2.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Hammer drill (a φ12 bit) ESD gloves Vacuum cleaner Heat gun Phillips screwdriver (M3 to M6) Flat-head screwdriver (M3 to M6) Rubber mallet COAX crimping tool Wire stripper Power cable crimping tool RJ45 crimping tool Diagonal plier Utility knife Level Network cable tester Adjustable wrench (size ≥ 32 mm [1.26 in.]) Torque screwdriver Marker (diameter ≤ 10 mm [0.39 in.]) Torque wrench 3mm or 5mm Size: 16 mm (0.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Fixed pulley(weight-bearing capacity > 500 kg or 1102.5 lb) Lifting sling Ladder 2.1.3 Requirements for Installation Personnel This section describes requirements for installation engineers. They must be qualified and trained, and familiar with correct operation methods and safety precautions before performing any operations.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Category Sections in eAN3710A Hardware Description 1.1.3 eAN3710A Indicators Auxiliary device 1.2.1 PSE 1.2.2 Dock Mounting kits 1.3.1 eAN3710A Mounting Kits 1.3.2 Dock Mounting Kits Cables 1.4.1 Cable List 2.2.2 Installation Options and Restrictions The eAN3710A can be installed on a wall or pole. Installation scenarios must meet heat-dissipation and waterproofing requirements of the eAN3710A.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-2 A eAN3710A installed on a pole Installation on a Wall The wall for installing eAN3710A must meet the following requirements: The wall can bear a load at least four times the weight of a eAN3710A. The screws must be tightened with a torque of 30 N·m. This ensures the screws work properly and the wall remains intact without cracks in it. Figure 2-3 shows the eAN3710A installed on a pole.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-3 A eAN3710A installed on a wall 2.2.3 Installation Clearance and Space Requirements This section describes the recommended and minimum clearances for a eAN3710A. Clearance for a eAN3710A When the eAN3710A is installed on a wall or pole, the minimum clearance is required for easy cabling and operation and maintenance (O&M). Based on the engineering practice, the recommendation for the installation clearance is provided.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-4 Clearances for installing a eAN3710A Installation Spacing Between eAN3710A Figure 2-5 lists the horizonta spacing between eAN3710A. Issue 01 (2016-12-26) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-5 Clearances for installing a eAN3710A Figure 2-6 lists the vertical spacing between eAN3710A. Issue 01 (2016-12-26) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-6 Clearances for installing a eAN3710A 2.2.4 Installation Environment Requirements The installation environment of a eAN3710A involves the running environment specifications for the eAN3710A. Running Environment Specifications Table 2-2 shows the environment specifications for the eAN3710A.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Item Specifications Absolute humidity 1 g/m3 to 30 g/m3 Atmospheric pressure 70 kPa to 106 kPa Protection class IP65 Requirements for the Installation Scenarios To ensure proper heat dissipation of the eAN3710A, the following requirements must be met: The eAN3710A cannot be installed in an enclosed cabinet without a cooling system. The eAN3710A cannot be installed in an enclosed camouflage box.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-8 Requirements for the vertical deviation angle of a eAN3710A (1) eAN3710A (2) Installation support (pole or wall) 2.3 Unpacking the Equipment This section describes how to unpack and check the delivered equipment to ensure that all the materials are included and intact.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide If... Then... The total number of the components is inconsistent with that recorded in the packing lists on all packing boxes Report the problems and causes to the local Huawei office. Step 2 Check the exterior of each packing box. If... Then... The exterior of each packing box is intact Go to Step 3. It is damaged or soaked Report the problems and causes to the local Huawei office.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-9 eAN3710A installation process 2.5 Obtaining the ESN Before installing the eAN3710A, record its electronic serial number (ESN) for future use during commissioning. Context The ESN uniquely identifies a device and is required during commissioning. Procedure Step 1 Remove the backup ESN label from the surface of the eAN3710A. as shown in Figure 2-10. Before removing the backup SN label, photograph it.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-10 Removing the ESN label Step 2 Record the ESN by using the template described in section 2.12.1 ESN Collection Template, and report it to the eAN3710A commissioning personnel. ----End 2.6 (Optional) Installing a Micro SD Card This section describes how to install a micro SD card in the eAN3710A. Prerequisites Software and configuration data files need to be prepared for the micro SD card to be installed.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-11 Installing a micro SD card Step 4 Cover the plate for the cabling cavity and use the screwdriver to tighten the screw. ----End 2.7 Installing the eAN3710A This section describes the eAN3710A installation process. 2.7.1 Installing eAN3710A on a Pole This section describes the procedure and precautions for installing an eAN3710A on a pole.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-12 Distance between the separate mounting kit and the ground It is recommended that the mounting kits be installed at a position 1200 mm (47.24 in.) to 1600 mm (59.06 in.) high above the ground. Step 2 Install the mounting kit, as shown in Figure 2-13. Figure 2-13 Installing the eAN3710A mounting kit 1. Determine a position for installing the eAN3710A.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-14 Securing the eAN3710A onto the mounting kit 1. Hang the two dowels on the top of the eAN3710A attachment plate onto the mounting kit, and push the eAN3710A until it snaps into place, as shown by illustrations a and b in Figure 2-14. 2. Use the M6 inner hexagon screwdriver to tighten the screw on the top of the attachment plate to 5 N·m (44.25 lbf·in.), as shown by illustration c in Figure 2-14. ----End 2.7.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Do not stand an eAN3710A upright because the RF ports cannot support the weight of the eAN3710A. Place a foam pad or cardboard under an eAN3710A to protect the eAN3710A housing from damage during the installation.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-16 Drilling a hole and inserting an expansion bolt assembly (1) M6x60 bolt 1. (2) Nut (3) Spring washer (4) Flat washer (5) Expansion tube Use a hammer drill with a φ8 bit to drill holes vertically at the marked anchor points. Ensure that the depth of each hole ranges from 45 mm (1.77 in.) to 50 mm (1.97 in.).
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-17 Securing the separate mounting kit (1) Nut (2) Spring washer (3) Flat washer Step 4 Hold the eAN3710A, hang the two dowels on the top of the eAN3710A attachment plate onto the separate mounting kit, and push the eAN3710A until it snaps into place, as shown by illustrations a and b in Figure 2-18.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-18 Securing the eAN3710A onto the mounting kit ----End 2.8 Installing the Auxiliary Devices This section describes the procedure and precautions for installing the auxiliary devices. 2.8.1 (Optional) Installing a Dock This section describes the procedure and precautions for installing a dock. Installing a Dock on a Pole This section describes the procedure and precautions for installing the Dock on a pole.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-19 Replacing the Dock mounting bracket Step 2 Route two hose clamps through the up and down mounting holes on the Dock separate mounting bracket, but do not route the steel belts through the locks, as shown in Figure 2-20. Issue 01 (2016-12-26) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-20 Routing hose clamps through the Dock separate mounting bracket Step 3 Put the Dock in the installation position, route two hose clamps through the pole and the steel belts through the locking connectors, partially tighten the screws, and use an M6 inner hexagon torque screwdriver to tighten the screws to 5 N·m (44.25 lbf·in.), as shown in Figure 2-21.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-21 Tightening hose clamps ----End Installing a Dock on a Wall This section describes the procedure and precautions for installing the Dock on a wall. Procedure Step 1 Place the Dock separate mounting bracket against the wall, use a level to verify that the mounting bracket is horizontally placed, and use a marker to mark anchor points, as shown in Figure 2-22.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-22 Marking anchor points (1) Level (2) Mounting hole (3) Marker (4) Dock separate mounting bracket Step 2 Drill holes at the anchor points, and install expansion bolt assemblies, as shown in Figure 2-23.
eAN3710A Hardware Installation Guide 1. 2 eAN3710A Hardware Installation Guide Use a hammer drill with a Ф8 drill bit to drill holes perpendicularly with the wall at the marked anchor points. Ensure that the depth of each hole ranges from 45 mm to 50 mm (1.77 in. to 1.97 in.) and each hole is of the same depth. To prevent inhalation or eye contact with dust, take adequate preventive measures when drilling holes. 2.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-25 Fitting the Dock onto the wall (1) Bolt (2) Flat washer (3) Spring washer (4) Nut ----End 2.8.2 (Optional) Installing the PSE This section describes the procedure and precautions for installing the PSE on a wall. Context The PSE can be installed only on an indoor wall. Procedure Step 1 Place the PSE against the wall, level it in the installation position, and mark anchor points.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-26 Marking anchor points Step 2 Drill holes and install expansion bolts. Figure 2-27 Drill holes and install expansion bolts Step 3 Install the PSE Issue 01 (2016-12-26) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-28 Install the PSE ----End 2.9 Installing eAN3710A Cables This section describes the procedures for installing eAN3710A cables and auxiliary devices cables. 2.9.1 Cabling Requirements Cables must be laid out according to the specified cabling requirements to prevent signal interference. If a cable listed below is not required, skip the cabling requirements of the cable.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Cables must be bound tightly and neatly. The sheaths of cables must not be damaged. Cable ties must face the same direction, and those at the same horizontal line must be in a straight line. The excess of indoor cable ties must be cut off. The excess of 5 mm (0.197 in.) of outdoor cable ties should be reserved, and the cut surfaces must be smooth without sharp edges.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide The external conductor of the coaxial wire and the shield layer of the shielded cable must have proper electrical contact with the metal surface of the equipment which they are connected to. PGND cables and signal cables must be installed separately. A certain distance must be reserved between them to prevent interference from each other. Switches or fuses must not be installed on the PGND cables.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide (1) PGND cable (2) RF jumper (3) Ethernet cable 2.9.3 Installing a PGND Cable This section describes the procedure for installing a PGND cable. Procedure Step 1 Prepare a eAN3710A PGND cable. 1. Cut the cable to a length suitable for the actual cable route. 2. Add OT terminals to both ends of the cable. Step 2 Install the eAN3710A PGND cable.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-31 Correct direction for crimping an OT terminal Step 3 Label the installed cable. Follow the same procedure when installing a Dock PGND cable. ----End 2.9.4 Installing a RF Jumper This section describes the procedure for installing an RF jumper. Procedure Step 1 Remove the dustproof cap from the ANT port to be used on the eAN3710A.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-32 Installing an RF jumper Step 3 Connect the other end of the eAN3710A RF jumper to the external antenna system. Step 4 Waterproof the connector of the RF jumper by waterproof tape, as shown in Figure2. Figure 2-33 Waterproof the connector of the RF jumper by waterproof tape (1) PVC insulation tape Issue 01 (2016-12-26) (2) Waterproof tape Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide During installation, ensure that no foreign substance, including sand, enters the waterproof tape. 1. Wrap a PVC insulation tape around the exposed area of the connector. The wrapped area is 15 mm away from the end of the connector, with a total length of 40 mm. 2. Ensure that dimensions (L x W) of the waterproof tape is 50 mm x 50 mm.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Wrap each layer of tape around each connector tightly and neatly, and ensure that the adhesive surface of each layer of tape overlaps more than 50% of the lower layer. When cutting off a cable tie, reserve a surplus length of 3 mm (0.12 in.) to 5 mm (0.20 in.). ----End Follow-up Procedure 1. Route the cable by following the instructions in section cabling requirements and use cable ties to bind the cable. 2.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-35 Installing an eAN3710A Ethernet cable (1) PoE port on the eAN3710A panel (2) Ethernet cable Step 3 Connect the RJ45 connector at the other end of the Ethernet cable to auxiliary devices port. ----End Follow-up Procedure 1. Route the cable, and then use a cable tie to bind the cable. 2. Label the installed cable. 2.9.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-36 Installing the PSE Cable (1) Ethernet cable between eAN3710A and PSE (2) Ethernet cable between PSE and External transmission device The total length of cables connected between the does not exceed 100 m. (3) PSE Power cable (2m) eAN3710A, PSE, and external transmission device 2.9.7 (Optional) Installing the Dock Ethernet Cable This section describes procedure and precautions for installing a Dock Ethernet cable.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide 2. Check whether the made RJ45 connector is qualified. 3. To complete the assembly of the other end, repeat Step 1.1 and Step 1.2. 4. Check whether the touch points on the connectors at both ends are normally conducted and well contacted and whether the connections are correct. Step 2 Installing the Dock Ethernet cable, as shown in Figure 2-37.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide power into the Dock. A Dock cascading power cable is used for power supply cascading between two Docks. Context Table 2-3 lists the specifications of the two power cables. Table 2-3 Power cable specifications Cable Dock input power cable Dock cascading power cable Color One End The Other End L Brown Cord end terminal (1.5 mm2) Depends on the external power device N Blue Cord end terminal (1.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Use a flat-head screwdriver to loosen the left ports on the L, N, and PE wiring posts inside the Dock. Connect one end of each cable to the corresponding port on the left side and tighten the wiring posts. Connect the other end to external devices. 3. Optional: Install Dock cascading power cables. Use a flat-head screwdriver to loosen the right ports on the L, N, and PE wiring posts inside one Dock.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-38 Installing power cables The protective cover of the power supply terminal is automatically secured. After the procedure is complete, tap the protective cover to restore it. ----End Issue 01 (2016-12-26) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide 2.10 Checking the eAN3710A Hardware Installation eAN3710A hardware installation checking includes hardware and cable installation checking. Table 2-4 lists the hardware installation checking items. Table 2-4 Hardware installation checking list No. Item 1 The installation position of each device strictly complies with the engineering design and meets clearance requirements. Sufficient space is reserved for equipment maintenance.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Table 2-6 Checklist for other cable connections No. Item 1 The connectors of the other cables must securely connected. 2 Labels on the cables are legible and bound based on the engineering requirements. The cables must be bound tightly and neatly. The sheaths of the cables must not be damaged. 3 Positions for routing the cables must meet requirements of the engineering design.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Figure 2-39 Power-on check procedure Checking the Indicator Status Table 2-7 Checking the indicator status If... then... RUN Steady white ETH Blinking white WIFI Off LINK Off Issue 01 (2016-12-26) The eAN3710A is running correctly. During the eAN3710A startup, there is no need to observe the indicator status.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide 2.12 Appendix This section describes reference information during installation. 2.12.1 ESN Collection Template This section describes the eAN3710A ESN collection template. The ESN collection template is used to record the installation position, and ESN of the site at the initial installation stage to facilitate subsequent commissioning and maintenance. Table 2-8 shows the ESN collection template.
eAN3710A Hardware Installation Guide 2 eAN3710A Hardware Installation Guide Related Document Description Installation Guide system. Issue 01 (2016-12-26) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.