BTS3902E WCDMA Installation Guide Issue Draft A Date 2011-06-30 HUAWEI TECHNOLOGIES CO., LTD.
Copyright © Huawei Technologies Co., Ltd. 2011. All rights reserved. No part of this document may be reproduced or transmitted in any form or by any means without prior written consent of Huawei Technologies Co., Ltd. Trademarks and Permissions and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd. All other trademarks and trade names mentioned in this document are the property of their respective holders.
BTS3902E WCDMA Installation Guide About This Document About This Document Purpose This document describes the procedures for installing a BTS3902E in different scenarios. It also provides checklists for hardware installation. Product Version The following table lists the product version related to this document.
BTS3902E WCDMA Installation Guide About This Document Unpack and check the delivered equipment to ensure that all the materials are included and intact. 5 Obtaining the ESN The Electronic Serial Number (ESN) is a unique identifier of a Network Element (NE). Record the ESN for later commissioning of the base station before installation.
BTS3902E WCDMA Installation Guide About This Document The general conventions that may be found in this document are defined as follows. Convention Description Times New Roman Normal paragraphs are in Times New Roman. Boldface Names of files, directories, folders, and users are in boldface. For example, log in as user root. Italic Book titles are in italics. Courier New Examples of information displayed on the screen are in Courier New.
BTS3902E WCDMA Installation Guide About This Document The keyboard operations that may be found in this document are defined as follows. Format Description Key Press the key. For example, press Enter and press Tab. Key 1+Key 2 Press the keys concurrently. For example, pressing Ctrl+Alt +A means the three keys should be pressed concurrently. Key 1, Key 2 Press the keys in turn. For example, pressing Alt, A means the two keys should be pressed in turn.
BTS3902E WCDMA Installation Guide Contents Contents About This Document...................................................................................................................iii 1 Changes in the BTS3902E WCDMA Installation Guide....................................................1-1 2 Installation Preparations...........................................................................................................2-1 2.1 Tools and Instruments...................................................
BTS3902E WCDMA Installation Guide Contents 9.5 (Optional) Installing a BTS3902E RF Jumper..............................................................................................9-13 9.6 Installing Transmission Cables.....................................................................................................................9-16 9.6.1 Installing an FE/GE Cable....................................................................................................................9-16 9.6.
BTS3902E WCDMA Installation Guide Figures Figures Figure 3-1 BTS3902E.......................................................................................................................................... 3-2 Figure 3-2 Dimensions of a BTS3902E without a housing..................................................................................3-2 Figure 3-3 Dimensions of a BTS3902E with a housing and antennas.................................................................
BTS3902E WCDMA Installation Guide Figures Figure 7-16 Drilling holes..................................................................................................................................7-14 Figure 7-17 Installing the adapting plate assembly ...........................................................................................7-15 Figure 7-18 Securing the securing pieces...........................................................................................................
BTS3902E WCDMA Installation Guide Figures Figure 9-16 Installing the FE/GE fiber optic cable............................................................................................9-18 Figure 9-17 Tightening the round connector......................................................................................................9-19 Figure 9-18 Installing an optical module...........................................................................................................
BTS3902E WCDMA Installation Guide Tables Tables Table 3-1 BTS3902E ports and indicators...........................................................................................................3-4 Table 3-2 BTS3902E indicators...........................................................................................................................3-5 Table 9-1 Specifications of the BTS3902E PGND cable and equipotential cable...............................................
BTS3902E WCDMA Installation Guide 1 1 Changes in the BTS3902E WCDMA Installation Guide Changes in the BTS3902E WCDMA Installation Guide This chapter describes the changes in the BTS3902E WCDMA Installation Guide. Draft A (2011-06-30) This is the draft. Issue Draft A (2011-06-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 2 Installation Preparations 2 Installation Preparations About This Chapter This chapter describes instrument preparations, and skills and qualifications that installation engineers must possess. 2.1 Tools and Instruments All required tools and instruments must be ready before the installation. 2.2 Skills and Requirements for Onsite Personnel Onsite personnel must be qualified and trained.
BTS3902E WCDMA Installation Guide 2 Installation Preparations 2.1 Tools and Instruments All required tools and instruments must be ready before the installation. Hammer drill (with a φ 12 bit, φ 14 bit, and φ 18 bit) Electrostatic discharge (ESD) gloves Vacuum cleaner Heat gun Phillips screwdriver (M3 to M6) Flat-head screwdriver (M3 to M6) Rubber mallet COAX crimping tool Wire stripper Utility knife Wire clippers Adjustable wrench (capacity ≥ 32 mm [1.26 in.
BTS3902E WCDMA Installation Guide 2 Installation Preparations Multimeter Marker (diameter ≤ 10 mm [0.39 in.]) — 2.2 Skills and Requirements for Onsite Personnel Onsite personnel must be qualified and trained. Before performing any operation, onsite personnel must be familiar with correct operation methods and safety precautions.
BTS3902E WCDMA Installation Guide 3 Information About the Installation 3 Information About the Installation About This Chapter This chapter describes the information that you must be familiar with before installing a BTS3902E, including the BTS3902E exterior, ports, installation options, physical supports, and installation clearance requirements. 3.1 BTS3902E Exterior Th BTS3902E has a modular design with its ports on the bottom. 3.
BTS3902E WCDMA Installation Guide 3 Information About the Installation 3.1 BTS3902E Exterior Th BTS3902E has a modular design with its ports on the bottom. Figure 3-1 shows the BTS3902E. The BTS3902E on the left has a housing, and the BTS3902E on the right does not have a housing. The camouflage shell is optional.
BTS3902E WCDMA Installation Guide 3 Information About the Installation Figure 3-3 Dimensions of a BTS3902E with a housing and antennas 3.2 BTS3902E Ports The BTS3902E ports are on the bottom, and the indicators are in the indicator on the front. Figure 3-4 shows the positions of the BTS3902E ports and indicators. Issue Draft A (2011-06-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 3 Information About the Installation Figure 3-4 Positions of the BTS3902E ports and indicators Table 3-1 describes the BTS3902E ports and indicators. Table 3-1 BTS3902E ports and indicators 3-4 Item Label Description Ports ANTA_TX/RX TX/RX port A ANTB_TX/RX TX/RX port B ANTC_SON SON antenna port ETH FE/GE electrical port OPT0 FE/GE optical port OPT1 FE/GE optical port MON Environment monitoring port for an RS485 input and four dry contact inputs.
BTS3902E WCDMA Installation Guide 3 Information About the Installation Item Label Description Indicators RUN For details, see BTS3902E Indicators. ALM ACT VSWR O/E O 3.3 BTS3902E Indicators A BTS3902E has six indicators, which indicate the running status of the BTS3902E. For details about the indicator positions on the BTS3902E panel, see BTS3902E Ports. Table 3-2 describes BTS3902E indicators.
BTS3902E WCDMA Installation Guide 3 Information About the Installation Indicator Color Status Description VSWR Red Off No VSWR alarm is generated. Blinking red (on for 1s and off for 1s) VSWR alarms are generated on the ANTB_TX/RX port. Steady red VSWR alarms are generated on the ANTA_TX/RX port. Blinking red (on for 0.125s and off for 0.125s) VSWR alarms are generated on the ANTA_TX/RX and ANTB_TX/RX ports. Steady on The OPT1 or ETH port is connected properly. Blinking (on for 0.
BTS3902E WCDMA Installation Guide 3 Information About the Installation Figure 3-5 Diameter of a pole Figure 3-6 shows a BTS3902E installed on a pole. Figure 3-6 BTS3902E installed on a pole Installing a BTS3902E on a Pole with the Diameter of 114 mm to 400 mm (4.49 in. to 15.75 in.) Figure 3-7 shows the diameter of a pole for installing a BTS3902E. Figure 3-7 Diameter of a pole Issue Draft A (2011-06-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 3 Information About the Installation Figure 3-8 shows a BTS3902E installed on a pole. Figure 3-8 BTS3902E installed on a pole Installing a BTS3902E on a Wall The wall on a BTS3902E is installed must meet the following requirements: l When a single BTS3902E is installed, the wall has a capacity of bearing at least four times the weight of the BTS3902E. l Expansion bolts must be tightened to 30 N·m (265.52 lbf·in.
BTS3902E WCDMA Installation Guide 3 Information About the Installation Figure 3-9 BTS3902E installed on a wall Installing a BTS3902E on a Wood Pole Figure 3-10 shows a BTS3902E installed on a wood pole. Figure 3-10 BTS3902E installed on a wood pole 3.5 Installation Clearance Requirements This section describes the clearance requirements for installing a BTS3902E on a pole, wall, or wood pole. Figure 3-11 shows the recommended installation clearance for a single BTS3902E.
BTS3902E WCDMA Installation Guide 3 Information About the Installation Figure 3-11 Recommended installation clearance for a single BTS3902E Figure 3-12 shows the minimum installation clearance for a single BTS3902E. Figure 3-12 Minimum installation clearance for a single BTS3902E Figure 3-13 shows the recommended installation clearance for two BTS3902Es installed side by side. 3-10 Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 3 Information About the Installation Figure 3-13 Recommended installation clearance for two BTS3902Es installed side by side Figure 3-14 shows the minimum installation clearance for two BTS3902Es installed side by side. Figure 3-14 Minimum installation clearance for two BTS3902Es installed side by side Figure 3-15 shows the recommended installation clearance for two BTS3902Es installed in a vertical line.
BTS3902E WCDMA Installation Guide 3 Information About the Installation Figure 3-15 Recommended installation clearance for two BTS3902Es installed in a vertical line (1) Pole (2) Wall Figure 3-16 shows the minimum installation clearance for two BTS3902Es installed in a vertical line. 3-12 Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 3 Information About the Installation Figure 3-16 Minimum installation clearance for two BTS3902Es installed in a vertical line (1) Pole Issue Draft A (2011-06-30) (2) Wall Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 4 Unpacking the Equipment 4 Unpacking the Equipment Unpack and check the delivered equipment to ensure that all the materials are included and intact. Context NOTE When transporting, moving, or installing the equipment, components, or parts, you must: l Prevent them from colliding with doors, walls, shelves, or other objects. l Wear clean gloves, and avoid touching the equipment, components, or parts with bare hands, sweatsoaked gloves, or dirty gloves.
BTS3902E WCDMA Installation Guide 4 Unpacking the Equipment If ... Then ... Types and quantity of the article tally with Sign the Packing List with the customer. those on the packing list There is any shipment shortage or wrong shipment Fill in and submit the Cargo Shortage and Mishandling Report. Articles are damaged. Fill in and submit the Article Replacement Report.
BTS3902E WCDMA Installation Guide 5 Obtaining the ESN 5 Obtaining the ESN The Electronic Serial Number (ESN) is a unique identifier of a Network Element (NE). Record the ESN for later commissioning of the base station before installation. Procedure Step 1 Use an M4 Phillips screwdriver to loosen the two captive screws on the housing, and then move the upper housing until it is stopped. Step 2 Record the ESN on the BTS3902E. l The ESN is printed on the label and BTS3902E.
BTS3902E WCDMA Installation Guide 5 Obtaining the ESN Figure 5-1 Obtaining the ESN Step 3 Report the ESN to the engineer for the commissioning of the base station. ----End 5-2 Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 6 Installation Process 6 Installation Process The BTS3902E installation process involves installing a BTS3902E and related cables, checking the BTS3902E hardware installation, and powering on the BTS3902E. Figure 6-1 shows the process of installing a BTS3902E. Issue Draft A (2011-06-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 6 Installation Process Figure 6-1 Process of installing the BTS3902E 6-2 Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 7 Installing a BTS3902E 7 Installing a BTS3902E About This Chapter This section describes the procedures for installing a BTS3902E. The BTS3902E can be installed on a pole, wall, or wood pole depending on the installation environment. 7.1 Mounting Kits for Installing a BTS3902E This section describes the brackets and attachment plate for installing a BTS3902E. 7.2 Installing a BTS3902E on a Pole with the Diameter of 60 mm to 114 mm (2.36 in. to 4.49 in.
BTS3902E WCDMA Installation Guide 7 Installing a BTS3902E 7.1 Mounting Kits for Installing a BTS3902E This section describes the brackets and attachment plate for installing a BTS3902E. Figure 7-1 shows the rear of a BTS3902E. Figure 7-1 Rear of a BTS3902E (1) Attachment plate Figure 7-2 shows the mounting bracket assembly for installing a BTS3902E.
BTS3902E WCDMA Installation Guide 7 Installing a BTS3902E Figure 7-3 Adapting plate assembly for installing a BTS3902E (1) Mounting hole group A (2) Mounting hole group B (3) Mounting hole group C (4) Adapting plates 7.2 Installing a BTS3902E on a Pole with the Diameter of 60 mm to 114 mm (2.36 in. to 4.49 in.) This section describes the procedure and precautions for installing a BTS3902E on a pole with the diameter of 60 mm to 114 mm (2.36 in. to 4.49 in.).
BTS3902E WCDMA Installation Guide 7 Installing a BTS3902E Figure 7-4 Installing the bracket assembly Step 4 Using a torque wrench, tighten the nuts to 40 N·m (354.03 lbf·in.) to secure the bracket assembly onto the pole, as shown in Figure 7-5. CAUTION Tighten the two dual-nut bolt assemblies alternatively. After the main and auxiliary brackets are secured properly, measure the spacing between the brackets on both sides and ensure that the spacing is the same on the two sides.
BTS3902E WCDMA Installation Guide 7 Installing a BTS3902E Figure 7-6 Installing the BTS3902E on the main mounting bracket ----End 7.3 Installing a BTS3902E on a Pole with the Diameter of 114 mm to 400 mm (4.49 in. to 15.75 in.) This section describes the procedure and precautions for installing a BTS3902E on a pole with the diameter of 114 mm to 400 mm (4.49 in. to 15.75 in.). Procedure Step 1 Install two adapting plates on the top and bottom of the main mounting bracket. Tighten two M6x14 screws to 4.
BTS3902E WCDMA Installation Guide 7 Installing a BTS3902E Figure 7-7 Installing the adapting plate assembly (1) Adapting plate (2) Screw (3) Main mounting bracket Step 2 Install two hose clamps through the mounting hole group B of the adapting plates, as shown in Figure 7-8. 7-6 Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 7 Installing a BTS3902E Figure 7-8 Installing the hose clamps (1) Mounting hole group B (2) Hose clamp Step 3 Install the securing piece, as shown in Figure 7-9. 1. Secure the hose clamp. 2. Use a level to check whether the adapting plate is on a horizontal plane. NOTE Secure the upper hose clamp before securing the lower clamp. Issue Draft A (2011-06-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 7 Installing a BTS3902E Figure 7-9 Securing the hose clamp Step 4 Install the BTS3902E on the main mounting bracket until the BTS3902E snaps shut, as shown in Figure 7-10. Figure 7-10 Installing the BTS3902E on the main mounting bracket 7-8 Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 7 Installing a BTS3902E ----End 7.4 Installing a BTS3902E on a Wall This section describes the procedure and precautions for installing a BTS3902E on a wall. Context CAUTION You must use adjustable torque tools to tighten all the screws and nuts to the requirements described in this document. Procedure Step 1 Install two adapting plates on the top and bottom of the main mounting bracket. Tighten two M6x14 screws to 4.8 N·m (42.48 lbf·in.
BTS3902E WCDMA Installation Guide 7 Installing a BTS3902E NOTE It is recommended that the BTS3902E be installed 8000 mm to 15000 mm (315 in. to 590.6 in.) above the floor. Figure 7-12 Marking the anchor points (1) Mounting hole group A (2) Level (3) Marker (4) Adapting plate Step 3 Drill holes at the anchor points, and then install expansion bolt assemblies, as shown in Figure 7-13. 7-10 Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 7 Installing a BTS3902E Figure 7-13 Drilling a hole and installing an expansion bolt assembly (1) M10x80 bolt 1. (2) Nut (3) Spring washer (4) Flat washer (5) Expansion tube Use a hammer drill with a φ12 bit to drill holes perpendicularly with the wall at the marked anchor points. Ensure that the depth of each hole ranges from 55 mm to 60 mm (2.17 in. to 2.36 in.).
BTS3902E WCDMA Installation Guide 7 Installing a BTS3902E CAUTION Ensure that the arrow on the main mounting bracket points upwards when installing the securing piece. Figure 7-14 Fitting the mounting piece on the expansion bolt (1) Insulation washer (2) Large flat washer (3) Spring washer (4) Nut Step 5 Install the BTS3902E on the main mounting bracket until the BTS3902E snaps shut, as shown in Figure 7-15. 7-12 Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 7 Installing a BTS3902E Figure 7-15 Installing the BTS3902E on the main mounting bracket ----End 7.5 Installing a BTS3902E on a Wood Pole This section describes the procedure and precautions for installing a BTS3902E on a wood pole. Procedure Step 1 Drill two holes with the diameter of 18 mm (0.71 in.) on the middle axis of the wood pole, ensuring that the inter-hole spacing is 203 mm (7.99 in.), as shown in Figure 7-16.
BTS3902E WCDMA Installation Guide 7 Installing a BTS3902E Figure 7-16 Drilling holes Step 2 Install two adapting plates on the top and bottom of the main mounting bracket. Tighten two M6x14 screws to 4.8 N·m (42.48 lbf·in.) to secure each of the plate, as shown in Figure 7-17. 7-14 Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 7 Installing a BTS3902E Figure 7-17 Installing the adapting plate assembly (1) Adapting plate (2) Screw (3) Main mounting bracket Step 3 Install the securing piece, as shown in Figure 7-18. 1. Align the mounting hole group C with the mounting holes in the wood pole. 2. Lead the two long M16 bolts with spacers through the upper and lower mounting holes. Issue Draft A (2011-06-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 7 Installing a BTS3902E Figure 7-18 Securing the securing pieces (1) Mounting hole group C (2) Bolt (3) Spacer Step 4 Tighten the nuts to 80 N·m (708.06 lbf·in.), as shown in Figure 7-19. 7-16 Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 7 Installing a BTS3902E Figure 7-19 Tightening nuts (1) Nut Step 5 Install the BTS3902E on the main mounting bracket until the BTS3902E snaps shut, as shown in Figure 7-20. Issue Draft A (2011-06-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 7 Installing a BTS3902E Figure 7-20 Installing the BTS3902E on the main mounting bracket ----End 7-18 Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 8 8 Installing an AC Surge Protection Box and Related Cables Installing an AC Surge Protection Box and Related Cables About This Chapter This chapter describes the dimensions, installation clearance requirements, and installation options of an AC surge protection box. It also describes the procedure for installing the surge protection box. An AC surge protection box can be configured when a BTS3902E is installed outdoors. 8.
8 Installing an AC Surge Protection Box and Related Cables BTS3902E WCDMA Installation Guide 8.1 Dimensions and Installation Clearance Requirements of an AC Surge Protection Box This section describes the dimensions and installation clearance requirements for an AC surge protection box. Figure 8-1 shows the dimensions of an AC surge protection box. Figure 8-1 Dimensions of an AC surge protection box Figure 8-2 shows the recommended installation clearance for an AC surge protection box.
BTS3902E WCDMA Installation Guide 8 Installing an AC Surge Protection Box and Related Cables Figure 8-3 shows the minimum installation clearance for an AC surge protection box. Figure 8-3 Minimum installation clearance for an AC surge protection box 8.2 Installation Options of an AC Surge Protection Box This section describes installation options of an AC surge protection box. An AC surge protection box can be installed on a pole, wall, or wood pole.
8 Installing an AC Surge Protection Box and Related Cables BTS3902E WCDMA Installation Guide Figure 8-5 AC surge protection box installed on a pole Installing an AC Surge Protection Box on a Pole with the Diameter of 114 mm to 400 mm (4.49 in. to 15.75 in.) Figure 8-6 shows the diameter of a pole for installing an AC surge protection box. Figure 8-6 Diameter of a pole Figure 8-7 shows an AC surge protection box installed on a pole.
BTS3902E WCDMA Installation Guide 8 Installing an AC Surge Protection Box and Related Cables Figure 8-7 AC surge protection box installed on a pole Installing an AC Surge Protection Box on a Wall Figure 8-8 shows an AC surge protection box installed on a wall. Figure 8-8 AC surge protection box installed on a wall Installing an AC Surge Protection Box on a Wood Pole Figure 8-9 shows an AC surge protection box installed on a wood pole.
8 Installing an AC Surge Protection Box and Related Cables BTS3902E WCDMA Installation Guide Figure 8-9 AC surge protection box installed on a wood pole 8.3 Installing an AC Surge Protection Box This section describes the procedure for installing an AC surge protection box. Procedure l Install an AC surge protection box on a pole, as shown in Figure 8-10. NOTE l When the diameter of the pole ranges from 60 mm to 114 mm (2.36 in. to 4.49 in.
BTS3902E WCDMA Installation Guide 8 Installing an AC Surge Protection Box and Related Cables 1. Loosen the hose clamp. 2. Lead the clamp through the gap between the rear mounting plate and the case of the AC surge protection box. 3. Install the hose clamp around the pole, and secure the clamp. NOTE If the diameter of the pole around which the clamp is installed is small, cut the extra part of the clamp. l Install an AC surge protection box on a wall. 1.
8 Installing an AC Surge Protection Box and Related Cables BTS3902E WCDMA Installation Guide Figure 8-12 Installing an expansion bolt (1) M10x65 bolt (2) Spring washer 10 (3) Plastic tube (4) Flat washer 10 (5) Expansion tube 3. Align the AC surge protection box with the holes in the wall, and tighten the expansion bolts to 30 N·m (265.52 lbf·in.), as shown in Figure 8-13. Figure 8-13 Installing an AC surge protection box l 8-8 Install an AC surge protection box on a wood pole.
BTS3902E WCDMA Installation Guide 8 Installing an AC Surge Protection Box and Related Cables 1. Place the rear mounting plate of the AC surge protection box against the wood pole, determine the anchor points on the middle axis, and then mark the anchor points. 2. Drill holes with the diameter of 12 mm (0.47 in.) at the anchor points through the wood pole, as shown in Figure 8-14. Figure 8-14 Drilling holes 3.
8 Installing an AC Surge Protection Box and Related Cables BTS3902E WCDMA Installation Guide Figure 8-15 Installing the AC surge protection box on the wood pole 4. 8-10 Tighten the nuts to 30 N·m (265.52 lbf·in.), as shown in Figure 8-16. Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 8 Installing an AC Surge Protection Box and Related Cables Figure 8-16 Tightening the nuts (1) Nut ----End 8.4 Installing Cables for an AC Surge Protection Box This section describes the procedure for installing cables for an AC surge protection box. Prerequisite Add OT terminals to the power cables for the AC surge protection box on the surge protection box side. For details, see Adding OT Terminals to the Power Cable Connected to the AC Surge Protection Box.
BTS3902E WCDMA Installation Guide 8 Installing an AC Surge Protection Box and Related Cables Figure 8-17 Opening the cover plate of the AC surge protection box (1) PG connector (2) Thread-lock sealing nut of the PG connector (3) Waterproof block NOTE Do not use the removed thread-lock sealing nut of the PG connector with the thread-lock sealing nuts on other surge protection boxes. Step 2 Glide the thread-lock sealing nut and then the PG connector over the power cable.
BTS3902E WCDMA Installation Guide 8 Installing an AC Surge Protection Box and Related Cables 1. Lead the power cable between the surge protection box and the external power device through the PG connector labeled IN. Connect the OT terminals of the brown, blue, and yellow/green core wires to the Lin, Nin, and GND ports on the surge protection box respectively. 2. Route the power cable between the BTS3902E and the AC surge protection box through the PG connector labeled OUT.
BTS3902E WCDMA Installation Guide 8 Installing an AC Surge Protection Box and Related Cables Figure 8-20 Securing AC power cables (1) Corrugated pipe (2) Connector between corrugated pipes Step 7 Bind the cables using cable ties at equal spacing of 30 cm (11.81 in.) and verify that the bend radius of the corrugated pipe is not less than 60 mm (2.36 in.). Step 8 Install the PGND cable and equipotential cable, as shown in Figure 8-21.
BTS3902E WCDMA Installation Guide 8 Installing an AC Surge Protection Box and Related Cables ----End Issue Draft A (2011-06-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 9 Installing Cables 9 Installing Cables About This Chapter This chapter describes the procedure and precautions for installing the PGND cables, power cables, and transmission cables for a BTS3902E in various scenarios. Based on actual requirements, and it also describes how to install an optional monitoring signal cable as required. 9.1 Cabling Requirements Cables must be routed according to the specified cabling requirements to prevent signal interference. 9.
BTS3902E WCDMA Installation Guide 9 Installing Cables This section describes the procedure for adding an easy power receptacle (pressfit type) connector.This section describes the procedure for adding OT terminals.This section describes the procedure for adding OT terminals to the surge protection box side of the power cable for the AC surge protection box. 9-2 Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 9 Installing Cables 9.1 Cabling Requirements Cables must be routed according to the specified cabling requirements to prevent signal interference. NOTE If a cable listed below is not required, skip the routing requirements of the cable. General Cabling Requirements The bending radius of the cables must meet the following specifications: l The bending radius of the 7/8'' feeder must be more than 250 mm (9.84 in.
BTS3902E WCDMA Installation Guide 9 Installing Cables l PGND cables and signal cables must be installed in an untangled and orderly fashion. A certain distance must be reserved between them to prevent interference from each other. l Fuses or switches must not be installed on the PGND cables. l Other devices must not be used for electrical connections of the PGND cables. l All the metal parts in the housing of the equipment must be reliably connected to the ground terminal.
BTS3902E WCDMA Installation Guide 9 Installing Cables Figure 9-1 Cable connections of a single BTS3902E implementing transmission over an electrical port (1) BTS3902E power cable (2) PGND cable (optional) (4) Fast Ethernet or gigabit Ethernet (5) BTS3902E monitoring signal (FE/GE) cable cable (optional) (3) Equipotential cable (optional) — Figure 9-2 shows the cable connections of a single BTS3902E implementing transmission over an optical port.
BTS3902E WCDMA Installation Guide 9 Installing Cables Figure 9-2 Cable connections of a single BTS3902E implementing transmission over an optical port (1) BTS3902E power cable (2) PGND cable (optional) (3) Equipotential cable (optional) (4) FE/GE fiber optic cable (5) BTS3902E monitoring signal cable (optional) — Figure 9-3 shows the cable connections of a single BTS3902E implementing power over Ethernet (POE) over an electrical port and transmission using a fiber optic cable.
BTS3902E WCDMA Installation Guide 9 Installing Cables Figure 9-3 Cable connections of a single BTS3902E implementing POE over an electrical port and transmission using a fiber optic cable (1) BTS3902E power cable (2) PGND cable (optional) (3) Equipotential cable (optional) (4) FE/GE cable (5) FE/GE fiber optic cable (6) BTS3902E monitoring signal cable (optional) Figure 9-4 shows the cable connections of two BTS3902Es implementing transmission and cascading using fiber optic cables.
BTS3902E WCDMA Installation Guide 9 Installing Cables Figure 9-4 Cable connections of two BTS3902Es implementing transmission and cascading using fiber optic cables (1) BTS3902E power cable (2) PGND cable (optional) (3) Equipotential cable (optional) (4) FE/GE fiber optic cable (5) BTS3902E monitoring signal cable (optional) (6) FE/GE fiber optic cable for cascading 9.
BTS3902E WCDMA Installation Guide 9 Installing Cables Cable One End The Other End Remarks Equipotential cable OT terminal (M6, 16 mm2 [0.025 in.2]) OT terminal (M6, 16 mm2 [0.025 in.2]) Green and yellow Procedure l Install the PGND cable when no AC surge protection box is installed, as shown in Figure 9-5. 1. Connect one end of the BTS3902E PGND terminal to the ground cable on the BTS3902E and the other end to the external ground bar.
8 Installing an AC Surge Protection Box and Related Cables BTS3902E WCDMA Installation Guide Figure 8-9 AC surge protection box installed on a wood pole 8.3 Installing an AC Surge Protection Box This section describes the procedure for installing an AC surge protection box. Procedure l Install an AC surge protection box on a pole, as shown in Figure 8-10. NOTE l When the diameter of the pole ranges from 60 mm to 114 mm (2.36 in. to 4.49 in.
BTS3902E WCDMA Installation Guide 8 Installing an AC Surge Protection Box and Related Cables 1. Loosen the hose clamp. 2. Lead the clamp through the gap between the rear mounting plate and the case of the AC surge protection box. 3. Install the hose clamp around the pole, and secure the clamp. NOTE If the diameter of the pole around which the clamp is installed is small, cut the extra part of the clamp. l Install an AC surge protection box on a wall. 1.
8 Installing an AC Surge Protection Box and Related Cables BTS3902E WCDMA Installation Guide Figure 8-12 Installing an expansion bolt (1) M10x65 bolt (2) Spring washer 10 (3) Plastic tube (4) Flat washer 10 (5) Expansion tube 3. Align the AC surge protection box with the holes in the wall, and tighten the expansion bolts to 30 N·m (265.52 lbf·in.), as shown in Figure 8-13. Figure 8-13 Installing an AC surge protection box l 8-8 Install an AC surge protection box on a wood pole.
BTS3902E WCDMA Installation Guide 8 Installing an AC Surge Protection Box and Related Cables 1. Place the rear mounting plate of the AC surge protection box against the wood pole, determine the anchor points on the middle axis, and then mark the anchor points. 2. Drill holes with the diameter of 12 mm (0.47 in.) at the anchor points through the wood pole, as shown in Figure 8-14. Figure 8-14 Drilling holes 3.
8 Installing an AC Surge Protection Box and Related Cables BTS3902E WCDMA Installation Guide Figure 8-15 Installing the AC surge protection box on the wood pole 4. 8-10 Tighten the nuts to 30 N·m (265.52 lbf·in.), as shown in Figure 8-16. Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 8 Installing an AC Surge Protection Box and Related Cables Figure 8-16 Tightening the nuts (1) Nut ----End 8.4 Installing Cables for an AC Surge Protection Box This section describes the procedure for installing cables for an AC surge protection box. Prerequisite Add OT terminals to the power cables for the AC surge protection box on the surge protection box side. For details, see Adding OT Terminals to the Power Cable Connected to the AC Surge Protection Box.
BTS3902E WCDMA Installation Guide 8 Installing an AC Surge Protection Box and Related Cables Figure 8-17 Opening the cover plate of the AC surge protection box (1) PG connector (2) Thread-lock sealing nut of the PG connector (3) Waterproof block NOTE Do not use the removed thread-lock sealing nut of the PG connector with the thread-lock sealing nuts on other surge protection boxes. Step 2 Glide the thread-lock sealing nut and then the PG connector over the power cable.
BTS3902E WCDMA Installation Guide 8 Installing an AC Surge Protection Box and Related Cables 1. Lead the power cable between the surge protection box and the external power device through the PG connector labeled IN. Connect the OT terminals of the brown, blue, and yellow/green core wires to the Lin, Nin, and GND ports on the surge protection box respectively. 2. Route the power cable between the BTS3902E and the AC surge protection box through the PG connector labeled OUT.
BTS3902E WCDMA Installation Guide 8 Installing an AC Surge Protection Box and Related Cables Figure 8-20 Securing AC power cables (1) Corrugated pipe (2) Connector between corrugated pipes Step 7 Bind the cables using cable ties at equal spacing of 30 cm (11.81 in.) and verify that the bend radius of the corrugated pipe is not less than 60 mm (2.36 in.). Step 8 Install the PGND cable and equipotential cable, as shown in Figure 8-21.
BTS3902E WCDMA Installation Guide 8 Installing an AC Surge Protection Box and Related Cables ----End Issue Draft A (2011-06-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 9 Installing Cables 9 Installing Cables About This Chapter This chapter describes the procedure and precautions for installing the PGND cables, power cables, and transmission cables for a BTS3902E in various scenarios. Based on actual requirements, and it also describes how to install an optional monitoring signal cable as required. 9.1 Cabling Requirements Cables must be routed according to the specified cabling requirements to prevent signal interference. 9.
BTS3902E WCDMA Installation Guide 9 Installing Cables This section describes the procedure for adding an easy power receptacle (pressfit type) connector.This section describes the procedure for adding OT terminals.This section describes the procedure for adding OT terminals to the surge protection box side of the power cable for the AC surge protection box. 9-2 Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3902E WCDMA Installation Guide 9 Installing Cables 9.1 Cabling Requirements Cables must be routed according to the specified cabling requirements to prevent signal interference. NOTE If a cable listed below is not required, skip the routing requirements of the cable. General Cabling Requirements The bending radius of the cables must meet the following specifications: l The bending radius of the 7/8'' feeder must be more than 250 mm (9.84 in.
BTS3902E WCDMA Installation Guide 9 Installing Cables l PGND cables and signal cables must be installed in an untangled and orderly fashion. A certain distance must be reserved between them to prevent interference from each other. l Fuses or switches must not be installed on the PGND cables. l Other devices must not be used for electrical connections of the PGND cables. l All the metal parts in the housing of the equipment must be reliably connected to the ground terminal.
BTS3902E WCDMA Installation Guide 9 Installing Cables Figure 9-1 Cable connections of a single BTS3902E implementing transmission over an electrical port (1) BTS3902E power cable (2) PGND cable (optional) (4) Fast Ethernet or gigabit Ethernet (5) BTS3902E monitoring signal (FE/GE) cable cable (optional) (3) Equipotential cable (optional) — Figure 9-2 shows the cable connections of a single BTS3902E implementing transmission over an optical port.
BTS3902E WCDMA Installation Guide 9 Installing Cables Figure 9-2 Cable connections of a single BTS3902E implementing transmission over an optical port (1) BTS3902E power cable (2) PGND cable (optional) (3) Equipotential cable (optional) (4) FE/GE fiber optic cable (5) BTS3902E monitoring signal cable (optional) — Figure 9-3 shows the cable connections of a single BTS3902E implementing power over Ethernet (POE) over an electrical port and transmission using a fiber optic cable.
BTS3902E WCDMA Installation Guide 9 Installing Cables Figure 9-3 Cable connections of a single BTS3902E implementing POE over an electrical port and transmission using a fiber optic cable (1) BTS3902E power cable (2) PGND cable (optional) (3) Equipotential cable (optional) (4) FE/GE cable (5) FE/GE fiber optic cable (6) BTS3902E monitoring signal cable (optional) Figure 9-4 shows the cable connections of two BTS3902Es implementing transmission and cascading using fiber optic cables.
BTS3902E WCDMA Installation Guide 9 Installing Cables Figure 9-4 Cable connections of two BTS3902Es implementing transmission and cascading using fiber optic cables (1) BTS3902E power cable (2) PGND cable (optional) (3) Equipotential cable (optional) (4) FE/GE fiber optic cable (5) BTS3902E monitoring signal cable (optional) (6) FE/GE fiber optic cable for cascading 9.
BTS3902E WCDMA Installation Guide 9 Installing Cables Cable One End The Other End Remarks Equipotential cable OT terminal (M6, 16 mm2 [0.025 in.2]) OT terminal (M6, 16 mm2 [0.025 in.2]) Green and yellow Procedure l Install the PGND cable when no AC surge protection box is installed, as shown in Figure 9-5. 1. Connect one end of the BTS3902E PGND terminal to the ground cable on the BTS3902E and the other end to the external ground bar.
BTS3902E WCDMA Installation Guide 9 Installing Cables Figure 9-25 Closing the housing and tightening the screws ----End 9.8 Checking the BTS3902E Hardware Installation This chapter describes how to check the hardware installation after a BTS3902E is installed. Table 9-3 provides the checklist for the BTS3902E hardware installation. Table 9-3 Checklist for the BTS3902E Hardware Installation SN Item 1 The position for each device conforms to the engineering drawing and meets the space requirement.
BTS3902E WCDMA Installation Guide 9 Installing Cables SN Item 5 The horizontal error of the BTS3902E is less than 3 mm (0.12 in.), and the vertical error is not more than 3 mm (0.12 in.). 6 The outdoor cables are properly installed. The vacant ports are covered with waterproof caps, and the caps are waterproofed. 7 None of power cables and PGND cables is short-circuited or reversely connected. In addition, these cables are not damaged or broken.
BTS3902E WCDMA Installation Guide 9 Installing Cables 9.9 Performing a Power-On Check on the BTS3902E This chapter describes the procedure for performing a power-on check on the BTS3902E. CAUTION After you unpack a BTS3902E, you must power it on within 24 hours. If you power off the BTS3902E for maintenance, you must restore power to it within 24 hours. Figure 9-26 shows the BTS3902E power-on check procedure.
BTS3902E WCDMA Installation Guide 9 Installing Cables 9.10 Appendix This section describes the procedure for adding an easy power receptacle (pressfit type) connector.This section describes the procedure for adding OT terminals.This section describes the procedure for adding OT terminals to the surge protection box side of the power cable for the AC surge protection box. 9.10.
BTS3902E WCDMA Installation Guide 9 Installing Cables NOTE Following is based on the power cable longer than or equal to 5 m (16.4 ft.). Step 3 Lead the power cable through corrugated pipes, and add a connector between two corrugated pipes, as shown in Figure 9-28. Figure 9-28 Leading the power cable through corrugated pipes Step 4 Join the corrugated pipes, as shown in Figure 9-29.
BTS3902E WCDMA Installation Guide 9 Installing Cables Figure 9-30 Determining the length of the power cable Step 6 Use a utility knife to strip the specified length of the sheath and shield layer off the power cable, as shown in Figure 9-31. Figure 9-31 Stripping the specified length of the sheath and shield layer Step 7 Strip the sheath off each core wire, as shown in Figure 9-32.
BTS3902E WCDMA Installation Guide 9 Installing Cables Procedure Step 1 Determine the position for installing the ground clip on the cable based on the actual cable route. Step 2 Use a utility knife to strip the sheath off the FE/GE cable for about 32 mm to expose the shield layer, as shown in Figure 9-34. CAUTION Do not damage the shield layer when stripping the sheath off the cable.
BTS3902E WCDMA Installation Guide 9 Installing Cables CAUTION l Wrap the tape around the clip from bottom up, then from top down, and finally from bottom up. Do not cut the tape until all the three layers of the tape are already wrapped. When wrapping tape, be sure that each layer of tape overlaps more than 50% of the preceding layer. l The degree between the ground cable and the FE/GE cable is not greater than 15°. When the FE/GE cable is routed vertically, the ground cable must be routed downwards.