BTS3202E LTE V100R004C00 Installation Guide Issue Draft A Date 2011-07-30 HUAWEI TECHNOLOGIES CO., LTD.
Copyright © Huawei Technologies Co., Ltd. 2011. All rights reserved. No part of this document may be reproduced or transmitted in any form or by any means without prior written consent of Huawei Technologies Co., Ltd. Trademarks and Permissions and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd. All other trademarks and trade names mentioned in this document are the property of their respective holders.
BTS3202E LTE Installation Guide About This Document About This Document Purpose This document describes the procedures for installing a BTS3202E in different scenarios. It also provides checklists for hardware installation. Product Version The following table lists the product version related to this document.
BTS3202E LTE Installation Guide About This Document Unpack and check the delivered equipment to ensure that all the materials are included and intact. 5 Obtaining the ESN The Electronic Serial Number (ESN) is a unique identifier of a Network Element (NE). Record the ESN for later commissioning of the base station before installation.
BTS3202E LTE Installation Guide About This Document Symbol Description Indicates a hazard with a high level of risk, which if not avoided, will result in death or serious injury. Indicates a hazard with a medium or low level of risk, which if not avoided, could result in minor or moderate injury. Indicates a potentially hazardous situation, which if not avoided, could result in equipment damage, data loss, performance degradation, or unexpected results.
BTS3202E LTE Installation Guide About This Document Convention Description { x | y | ... }* Optional items are grouped in braces and separated by vertical bars. A minimum of one item or a maximum of all items can be selected. [ x | y | ... ]* Optional items are grouped in brackets and separated by vertical bars. Several items or no item can be selected. GUI Conventions The GUI conventions that may be found in this document are defined as follows.
BTS3202E LTE Installation Guide Contents Contents About This Document.....................................................................................................................ii 1 Changes in the BTS3202E LTE Installation Guide.................................................................1 2 Installation Preparations..............................................................................................................2 2.1 Tools and Instruments..........................................
BTS3202E LTE Installation Guide Contents 8.4 Installing Cables for an AC Surge Protection Box...........................................................................................72 9 Installing Cables..........................................................................................................................77 9.1 Cabling Requirements......................................................................................................................................78 9.
BTS3202E LTE Installation Guide 1 1 Changes in the BTS3202E LTE Installation Guide Changes in the BTS3202E LTE Installation Guide This chapter describes the changes in the BTS3202E LTE Installation Guide. Draft A (2011-07-30) This is the draft. Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 2 Installation Preparations 2 Installation Preparations About This Chapter This chapter describes instrument preparations, and skills and qualifications that installation engineers must possess. 2.1 Tools and Instruments All required tools and instruments must be ready before the installation. 2.2 Skills and Requirements for Onsite Personnel Onsite personnel must be qualified and trained.
BTS3202E LTE Installation Guide 2 Installation Preparations 2.1 Tools and Instruments All required tools and instruments must be ready before the installation. Hammer drill (with a φ 12 bit, φ 14 bit, and φ 18 bit) Electrostatic discharge (ESD) gloves Vacuum cleaner Heat gun Phillips screwdriver (M3 to M6) Flat-head screwdriver (M3 to M6) Rubber mallet COAX crimping tool Wire stripper Utility knife Wire clippers Adjustable wrench (capacity ≥ 32 mm [1.26 in.
BTS3202E LTE Installation Guide 2 Installation Preparations Multimeter Marker (diameter ≤ 10 mm [0.39 in.]) — 2.2 Skills and Requirements for Onsite Personnel Onsite personnel must be qualified and trained. Before performing any operation, onsite personnel must be familiar with correct operation methods and safety precautions.
BTS3202E LTE Installation Guide 3 Information About the Installation 3 Information About the Installation About This Chapter This chapter describes the information that you must be familiar with before installing a BTS3202E, including the BTS3202E exterior, ports, installation options, physical supports, and installation clearance requirements. 3.1 BTS3202E Exterior The BTS3202E has a modular design with its ports on the bottom. 3.
BTS3202E LTE Installation Guide 3 Information About the Installation 3.1 BTS3202E Exterior The BTS3202E has a modular design with its ports on the bottom. Figure 3-1 shows the BTS3202E. The BTS3202E on the left has a housing, and the BTS3202E on the right does not have a housing. The camouflage shell is optional.
BTS3202E LTE Installation Guide 3 Information About the Installation Figure 3-3 Dimensions of a BTS3202E with a housing and antennas NOTE The figure shows the dimensions of the two types of BTS3202E. Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 3 Information About the Installation 3.2 BTS3202E Ports The BTS3202E ports are on the bottom, and the indicators are in the indicator on the front. Figure 3-4 shows the positions of the BTS3202E ports and indicators. Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 3 Information About the Installation Figure 3-4 Positions of the BTS3202E ports and indicators Table 3-1 describes the BTS3202E ports and indicators. Table 3-1 BTS3202E ports and indicators Item Label Description Ports ANTA_TX/RX TX/RX port A ANTB_TX/RX TX/RX port B ANTC_SON SON antenna port ETH FE/GE electrical port OPT FE/GE optical port RGPS RGPS port MON Environment monitoring port for an RS485 input and four dry contact inputs.
BTS3202E LTE Installation Guide 3 Information About the Installation Item Indicators Label Description DBG Port for commissioning, clock test, or software upgrade RUN For details, see BTS3202E Indicators. ALM ACT VSWR O/E O 3.3 BTS3202E Indicators A BTS3202E has six indicators, which indicate the running status of the BTS3202E. For details about the indicator positions on the BTS3202E panel, see BTS3202E Ports. Table 3-2 describes BTS3202E indicators.
BTS3202E LTE Installation Guide 3 Information About the Installation Indicator VSWR O/E O Color Red Green Green Status Description Blinking (on for 1s and off for 1s) The BTS3202E is working properly with TX channels disabled. Off No VSWR alarm is generated. Blinking red (on for 1s and off for 1s) VSWR alarms are generated on the ANTB_TX/RX port. Steady red VSWR alarms are generated on the ANTA_TX/RX port. Blinking red (on for 0.125s and off for 0.
BTS3202E LTE Installation Guide 3 Information About the Installation Figure 3-5 Diameter of a pole Figure 3-6 shows a BTS3902E installed on a pole. Figure 3-6 BTS3902E installed on a pole Installing a BTS3902E on a Pole with the Diameter of 114 mm to 400 mm (4.49 in. to 15.75 in.) Figure 3-7 shows the diameter of a pole for installing a BTS3902E. Figure 3-7 Diameter of a pole Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 3 Information About the Installation Figure 3-8 shows a BTS3902E installed on a pole. Figure 3-8 BTS3902E installed on a pole Installing a BTS3902E on a Wall The wall on a BTS3902E is installed must meet the following requirements: l When a single BTS3902E is installed, the wall has a capacity of bearing at least four times the weight of the BTS3902E. l Expansion bolts must be tightened to 30 N·m (265.52 lbf·in.
BTS3202E LTE Installation Guide 3 Information About the Installation Figure 3-9 BTS3902E installed on a wall Installing a BTS3902E on a Wood Pole Figure 3-10 shows a BTS3902E installed on a wood pole. Figure 3-10 BTS3902E installed on a wood pole 3.5 Installation Clearance Requirements This section describes the clearance requirements for installing a BTS3902E on a pole, wall, or wood pole. Figure 3-11 shows the recommended installation clearance for a single BTS3902E.
BTS3202E LTE Installation Guide 3 Information About the Installation Figure 3-11 Recommended installation clearance for a single BTS3902E Figure 3-12 shows the minimum installation clearance for a single BTS3902E. Figure 3-12 Minimum installation clearance for a single BTS3902E Figure 3-13 shows the recommended installation clearance for two BTS3902Es installed side by side. Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 3 Information About the Installation Figure 3-13 Recommended installation clearance for two BTS3902Es installed side by side Figure 3-14 shows the minimum installation clearance for two BTS3902Es installed side by side. Figure 3-14 Minimum installation clearance for two BTS3902Es installed side by side Figure 3-15 shows the recommended installation clearance for two BTS3902Es installed in a vertical line.
BTS3202E LTE Installation Guide 3 Information About the Installation Figure 3-15 Recommended installation clearance for two BTS3902Es installed in a vertical line (1) Pole (2) Wall Figure 3-16 shows the minimum installation clearance for two BTS3902Es installed in a vertical line. Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 3 Information About the Installation Figure 3-16 Minimum installation clearance for two BTS3902Es installed in a vertical line (1) Pole Issue Draft A (2011-07-30) (2) Wall Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 4 Unpacking the Equipment 4 Unpacking the Equipment Unpack and check the delivered equipment to ensure that all the materials are included and intact. Context NOTE When transporting, moving, or installing the equipment, components, or parts, you must: l Prevent them from colliding with doors, walls, shelves, or other objects. l Wear clean gloves, and avoid touching the equipment, components, or parts with bare hands, sweatsoaked gloves, or dirty gloves.
BTS3202E LTE Installation Guide 4 Unpacking the Equipment If ... Then ... Types and quantity of the article tally with Sign the Packing List with the customer. those on the packing list There is any shipment shortage or wrong shipment Fill in and submit the Cargo Shortage and Mishandling Report. Articles are damaged. Fill in and submit the Article Replacement Report.
BTS3202E LTE Installation Guide 5 Obtaining the ESN 5 Obtaining the ESN The Electronic Serial Number (ESN) is a unique identifier of a Network Element (NE). Record the ESN for later commissioning of the base station before installation. Procedure Step 1 Use an M4 Phillips screwdriver to loosen the two captive screws on the housing, and then move the upper housing until it is stopped. Step 2 Record the ESN on the BTS3202E. l The ESN is printed on the label and BTS3202E.
BTS3202E LTE Installation Guide 5 Obtaining the ESN Figure 5-1 Obtaining the ESN Step 3 Report the ESN to the engineer for the commissioning of the base station. ----End Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 6 Installation Process 6 Installation Process The BTS3902E installation process involves installing a BTS3902E and related cables, checking the BTS3902E hardware installation, and powering on the BTS3902E. Figure 6-1 shows the process of installing a BTS3902E. Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 6 Installation Process Figure 6-1 Process of installing the BTS3902E Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E 7 Installing a BTS3902E About This Chapter This section describes the procedures for installing a BTS3902E. The BTS3902E can be installed on a pole, wall, or wood pole depending on the installation environment. 7.1 Mounting Kits for Installing a BTS3202E This section describes the brackets and attachment plate for installing a BTS3202E. 7.2 Installing a BTS3202E on a Pole with the Diameter of 60 mm to 114 mm (2.36 in. to 4.49 in.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E 7.1 Mounting Kits for Installing a BTS3202E This section describes the brackets and attachment plate for installing a BTS3202E. Figure 7-1 shows the rear of a BTS3202E. Figure 7-1 Rear of a BTS3202E (1) Attachment plate Figure 7-2 shows the mounting bracket assembly for installing a BTS3202E.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-3 Adapting plate assembly for installing a BTS3202E (1) Mounting hole group A (2) Mounting hole group B (3) Mounting hole group C (4) Adapting plates 7.2 Installing a BTS3202E on a Pole with the Diameter of 60 mm to 114 mm (2.36 in. to 4.49 in.) This section describes the procedure and precautions for installing a BTS3202E on a pole with the diameter of 60 mm to 114 mm (2.36 in. to 4.49 in.).
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-4 Installing the bracket assembly NOTE Verify that the arrow on the main mounting bracket is pointing up. Step 4 Using a torque wrench, tighten the nuts to 40 N·m (354.03 lbf·in.) to secure the bracket assembly onto the pole, as shown in Figure 7-5. CAUTION Tighten the two dual-nut bolt assemblies alternatively.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-6 Installing the BTS3202E on the main mounting bracket ----End 7.3 Installing a BTS3202E on a Pole with the Diameter of 114 mm to 400 mm (4.49 in. to 15.75 in.) This section describes the procedure and precautions for installing a BTS3202E on a pole with the diameter of 114 mm to 400 mm (4.49 in. to 15.75 in.). Procedure Step 1 Install two adapting plates on the top and bottom of the main mounting bracket. Tighten two M6x14 screws to 4.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-7 Installing the adapting plate assembly (1) Adapting plate (2) Screw (3) Main mounting bracket Step 2 Install two hose clamps through the mounting hole group B of the adapting plates, as shown in Figure 7-8. Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-8 Installing the hose clamps (1) Mounting hole group B (2) Hose clamp Step 3 Install the securing piece, as shown in Figure 7-9. 1. Secure the hose clamp. 2. Use a level to check whether the adapting plate is on a horizontal plane. NOTE Secure the upper hose clamp before securing the lower clamp. Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-9 Securing the hose clamp Step 4 Install the BTS3202E on the main mounting bracket until the BTS3202E snaps shut, as shown in Figure 7-10. Figure 7-10 Installing the BTS3202E on the main mounting bracket Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E ----End 7.4 Installing a BTS3202E on a Wall This section describes the procedure and precautions for installing a BTS3202E on a wall. Context CAUTION You must use adjustable torque tools to tighten all the screws and nuts to the requirements described in this document. Procedure Step 1 Install two adapting plates on the top and bottom of the main mounting bracket. Tighten two M6x14 screws to 4.8 N·m (42.48 lbf·in.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E NOTE It is recommended that the BTS3202E be installed 8000 mm to 15000 mm (315 in. to 590.6 in.) above the floor. Figure 7-12 Marking the anchor points (1) Mounting hole group A (2) Level (3) Marker (4) Adapting plate Step 3 Drill holes at the anchor points, and then install expansion bolt assemblies, as shown in Figure 7-13. Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-13 Drilling a hole and installing an expansion bolt assembly (1) M10x80 bolt 1. (2) Nut (3) Spring washer (4) Flat washer (5) Expansion tube Use a hammer drill with a φ12 bit to drill holes perpendicularly with the wall at the marked anchor points. Ensure that the depth of each hole ranges from 55 mm to 60 mm (2.17 in. to 2.36 in.).
BTS3202E LTE Installation Guide 7 Installing a BTS3902E CAUTION Ensure that the arrow on the main mounting bracket points upwards when installing the securing piece. Figure 7-14 Fitting the mounting piece on the expansion bolt (1) Insulation washer (2) Large flat washer (3) Spring washer (4) Nut Step 5 Install the BTS3202E on the main mounting bracket until the BTS3202E snaps shut, as shown in Figure 7-15.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-15 Installing the BTS3202E on the main mounting bracket ----End 7.5 Installing a BTS3202E on a Wood Pole This section describes the procedure and precautions for installing a BTS3202E on a wood pole. Procedure Step 1 Drill two holes with the diameter of 18 mm (0.71 in.) on the middle axis of the wood pole, ensuring that the inter-hole spacing is 203 mm (7.99 in.), as shown in Figure 7-16.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-16 Drilling holes Step 2 Install two adapting plates on the top and bottom of the main mounting bracket. Tighten two M6x14 screws to 4.8 N·m (42.48 lbf·in.) to secure each of the plate, as shown in Figure 7-17. Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-17 Installing the adapting plate assembly (1) Adapting plate (2) Screw (3) Main mounting bracket Step 3 Install the securing piece, as shown in Figure 7-18. 1. Align the mounting hole group C with the mounting holes in the wood pole. 2. Lead the two long M16 bolts with spacers through the upper and lower mounting holes. Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-18 Securing the securing pieces (1) Mounting hole group C (2) Bolt (3) Spacer Step 4 Tighten the nuts to 80 N·m (708.06 lbf·in.), as shown in Figure 7-19. Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-19 Tightening nuts (1) Spacer (2) Nut Step 5 Install the BTS3202E on the main mounting bracket until the BTS3202E snaps shut, as shown in Figure 7-20. Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-20 Installing the BTS3202E on the main mounting bracket ----End 7.6 Installing BTS3202Es on an IFS06 This section describes the procedure and precautions for installing BTS3202Es on an IFS06. 7.6.1 Assembling the IFS06 This chapter describes the procedure for assembling the IFS06. Procedure Step 1 Use four M12x30 bolt assemblies to secure the rear feet to the main frame, as shown in Figure 7-21.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-21 Installing the rear feet Step 2 Rotate the IFS06 by 180°, and then use six M12x30 bolt assemblies to secure the front feet to the main frame, as shown in Figure 7-22. Figure 7-22 Installing the front feet Step 3 Move down the adjustable beam from the 2 m high position to the 1.8 m high position, as shown in Figure 7-23. NOTE In the height-restricted scenario, move the adjustable beam to the 1.8 m high position.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-23 Moving down the adjustable beam Step 4 Fit the tabs of the cable rack into the corresponding slots on the columns of the IFS06, as shown in Figure 7-24. Figure 7-24 Installing the cable rack NOTE In the height-unrestricted scenario, fit the tabs of the cable rack into the slots for the height-unrestricted scenario. In the height-restricted scenario, fit the tabs of the cable rack into the slots for the height-restricted scenario.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E (1) Slot for installing the cable rack in the heightunrestricted scenario (2) Slot for installing the cable rack in the heightrestricted scenario ----End 7.6.2 Installing the IFS06 This chapter describes the procedure for installing the IFS06 on the concrete floor and ESD floor. Installing the IFS06 on the Concrete Floor This section describes the procedure for installing the IFS06 on the concrete floor.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-25 Marking anchor points (1) Wall (2) Front (3) Left Step 2 Drill holes at the anchor points and install the expansion bolt assemblies. 1. Use a hammer drill with bit 16 to drill holes at the marked anchor points. Ensure that the depth of each hole ranges from 52 mm to 60 mm, as shown in Figure 7-26. Use a vacuum cleaner to clear the dust inside and around the holes.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E CAUTION Take proper safety measures before drilling holes to protect your eyes and respiratory tract against the dust. 2. Assemble the expansion bolt assembly by referring to Figure 7-27, slightly tighten the expansion bolt, and then insert it into the hole vertically. Figure 7-27 Assembling an expansion bolt (1) M12x60 bolt 3.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Step 3 Install the bolts in the corresponding mounting holes on the IFS06, as shown in Figure 7-30. Figure 7-30 Installing the bolts (1) M12x60 bolt (2) Spring washer (3) Flat washer (4) Insulation washer 1. Place the IFS06 in the position for installation, and then align the mounting holes on the IFS06 with the anchor points on the floor. 2.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-32 Checking and adjusting the level of the IFS06 (1) Level 3. (2) Adjusting pad Add adjusting pads to ensure that the feet and bottom beam of the IFS06 are on a horizontal plane, as shown in Figure 7-32. NOTE The adjusting pads must be added at the expansion bolt assemblies. 4. Tightening the bolts using a socket wrench, as shown in Figure 7-33.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-34 Support for installing the ESD floor (1) Mounting holes for the ESD floor (2) Support (3) Mounting hole for the concrete floor The height of an ESD floor refers to the spacing between the concrete floor and the upper surface of the ESD floor.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-35 Marking anchor points (1) Wall (2) Front (3) Left Step 2 Drill holes on the ESD floor, as shown in Figure 7-36. Ensure that the hammer drill penetrates the ESD floor. Use a vacuum cleaner to clear the dust inside and around the holes. If the inter-hole spacing is too wide or too narrow, locate and drill holes again.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E CAUTION Take proper safety measures before drilling holes to protect your eyes and respiratory tract against the dust. Step 3 Install the support for installing the ESD floor, as shown in Figure 7-37. Figure 7-37 Installing the support (1) M12x70 bolt (2, 5) Spring washer 12 (3,6) Flat washer 12 (4) M12x60 bolt 1.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-38 Removing the bolts Step 5 Install the IFS06 on the ESD Floor, as shown in Figure 7-39. Figure 7-39 Install the IFS06. (1) M12x70 bolt (2) Spring washer (3) Flat washer (4) Insulating washer Step 6 Use a level to check whether the feet of the ICR are on a horizontal plane. If not, add adjusting pads to ensure that the feet of the ICR are on a horizontal plane. 1. Pre-tighten the bolts, as shown in Figure 7-40.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-40 Pre-tightening the bolts 2. Use a level to check whether the feet and bottom beam of the ICR are on a horizontal plane, as shown in Figure 7-41. Figure 7-41 Checking and adjusting the level of the ICR (1) Level 3. (2) Adjusting pad Add adjusting pads to ensure that the feet and bottom beam of the ICR are on a horizontal plane, as shown in Figure 7-41. NOTE The adjusting pads should be added at the expansion bolt assemblies. 4.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E 7.6.3 Installing a Main Bracket This section describes the procedure for installing a main bracket. Context NOTE l Install BTS3202Es in the sequence from bottom to top and from left to right. l The contact pieces on the main bracket are locked before RRUs are mounted. l Rubber washers are easily pressed or broken. l If the installation clearance is insufficient, BTS3202Es must be first mounted on the side where there is the least space.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E (1) Spring washer l (2) Rubber washer (3) Label Height-restricted scenario In the height-restricted scenario, main brackets are installed on beam 2 and beam 4, as shown in Figure 7-44. For details about how to install a main bracket, see the label on an IFS06. Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-44 Installing main brackets in the height-restricted scenario (1) Spring washer Issue Draft A (2011-07-30) (2) Rubber washer Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E ----End 7.6.4 Installing an IFS06 PGND Cable A PGND cable connects a ground screw on an IFS06 to the onsite ground bar to ensure proper grounding of the IFS06. Context Table 7-1 lists the specifications of a PGND cable. Table 7-1 Specifications of a PGND cable Cable One End The Other End Remarks PGND cable OT terminal (M8) OT terminal (M8) Green and yellow cable (16 mm2) NOTE The cable route depends on actual requirements.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-45 Installing a PGND cable (1) Ground bar 1 (2) Ground bar 2 NOTE When installing the PGND cable, tightly press the OT terminal in the correct direction, as shown in Figure 7-46. Figure 7-46 Installing an OT terminal in the correct manner Step 2 Route the cable by referring to Cabling Requirements, and then use cable ties to bind the cable.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Step 3 Label the cable by referring to Attaching a Cable-Tying Label. ----End 7.6.5 Installing BTS3202Es This section describes the procedures for installing BTS3202Es. Context NOTE l Place a foam pad or cardboard under a BTS3202E to protect the housing from any damage. l Do not stand a BTS3202E on a floor because the load-bearing capacity of a BTS3202E at the bottom is low.
BTS3202E LTE Installation Guide 7 Installing a BTS3902E Figure 7-48 Installing the BTS3202E on the main bracket NOTE Install lower-level BTS3202Es before installing upper-level BTS3202Es. ----End Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 8 8 Installing an AC Surge Protection Box and Related Cables Installing an AC Surge Protection Box and Related Cables About This Chapter This chapter describes the dimensions, installation clearance requirements, and installation options of an AC surge protection box. It also describes the procedure for installing the surge protection box. An AC surge protection box can be configured when a BTS3202E is installed outdoors. 8.
BTS3202E LTE Installation Guide 8 Installing an AC Surge Protection Box and Related Cables 8.1 Dimensions and Installation Clearance Requirements of an AC Surge Protection Box This section describes the dimensions and installation clearance requirements for an AC surge protection box. Figure 8-1 shows the dimensions of an AC surge protection box. Figure 8-1 Dimensions of an AC surge protection box Figure 8-2 shows the recommended installation clearance for an AC surge protection box.
BTS3202E LTE Installation Guide 8 Installing an AC Surge Protection Box and Related Cables Figure 8-3 shows the minimum installation clearance for an AC surge protection box. Figure 8-3 Minimum installation clearance for an AC surge protection box 8.2 Installation Options of an AC Surge Protection Box This section describes installation options of an AC surge protection box. An AC surge protection box can be installed on a pole, wall, or wood pole.
BTS3202E LTE Installation Guide 8 Installing an AC Surge Protection Box and Related Cables Figure 8-5 AC surge protection box installed on a pole Installing an AC Surge Protection Box on a Pole with the Diameter of 114 mm to 400 mm (4.49 in. to 15.75 in.) Figure 8-6 shows the diameter of a pole for installing an AC surge protection box. Figure 8-6 Diameter of a pole Figure 8-7 shows an AC surge protection box installed on a pole.
BTS3202E LTE Installation Guide 8 Installing an AC Surge Protection Box and Related Cables Figure 8-7 AC surge protection box installed on a pole Installing an AC Surge Protection Box on a Wall Figure 8-8 shows an AC surge protection box installed on a wall. Figure 8-8 AC surge protection box installed on a wall Installing an AC Surge Protection Box on a Wood Pole Figure 8-9 shows an AC surge protection box installed on a wood pole.
BTS3202E LTE Installation Guide 8 Installing an AC Surge Protection Box and Related Cables Figure 8-9 AC surge protection box installed on a wood pole 8.3 Installing an AC Surge Protection Box This section describes the procedure for installing an AC surge protection box. Procedure l Install an AC surge protection box on a pole, as shown in Figure 8-10. NOTE l When the diameter of the pole ranges from 60 mm to 114 mm (2.36 in. to 4.49 in.
BTS3202E LTE Installation Guide 8 Installing an AC Surge Protection Box and Related Cables 1. Loosen the hose clamp. 2. Lead the clamp through the gap between the rear mounting plate and the case of the AC surge protection box. 3. Install the hose clamp around the pole, and secure the clamp. NOTE If the diameter of the pole around which the clamp is installed is small, cut the extra part of the clamp. l Install an AC surge protection box on a wall. 1.
BTS3202E LTE Installation Guide 8 Installing an AC Surge Protection Box and Related Cables Figure 8-12 Installing an expansion bolt (1) M10x65 bolt (2) Spring washer 10 (3) Plastic tube (4) Flat washer 10 (5) Expansion tube 3. Align the AC surge protection box with the holes in the wall, and tighten the expansion bolts to 30 N·m (265.52 lbf·in.), as shown in Figure 8-13. Figure 8-13 Installing an AC surge protection box l Install an AC surge protection box on a wood pole.
BTS3202E LTE Installation Guide 8 Installing an AC Surge Protection Box and Related Cables 1. Place the rear mounting plate of the AC surge protection box against the wood pole, determine the anchor points on the middle axis, and then mark the anchor points. 2. Drill holes with the diameter of 12 mm (0.47 in.) at the anchor points through the wood pole, as shown in Figure 8-14. Figure 8-14 Drilling holes 3.
BTS3202E LTE Installation Guide 8 Installing an AC Surge Protection Box and Related Cables Figure 8-15 Installing the AC surge protection box on the wood pole 4. Issue Draft A (2011-07-30) Tighten the nuts to 30 N·m (265.52 lbf·in.), as shown in Figure 8-16. Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 8 Installing an AC Surge Protection Box and Related Cables Figure 8-16 Tightening the nuts (1) Nut ----End 8.4 Installing Cables for an AC Surge Protection Box This section describes the procedure for installing cables for an AC surge protection box. Prerequisite Add OT terminals to the power cables for the AC surge protection box on the surge protection box side. For details, see Adding OT Terminals to the Power Cable Connected to the AC Surge Protection Box.
BTS3202E LTE Installation Guide 8 Installing an AC Surge Protection Box and Related Cables Figure 8-17 Opening the cover plate of the AC surge protection box (1) PG connector (2) Thread-lock sealing nut of the PG connector (3) Waterproof block NOTE Do not use the removed thread-lock sealing nut of the PG connector with the thread-lock sealing nuts on other surge protection boxes. Step 2 Glide the thread-lock sealing nut and then the PG connector over the power cable.
BTS3202E LTE Installation Guide 8 Installing an AC Surge Protection Box and Related Cables 1. Lead the power cable between the surge protection box and the external power device through the PG connector labeled IN. Connect the OT terminals of the brown, blue, and yellow/green core wires to the Lin, Nin, and GND ports on the surge protection box respectively. 2. Route the power cable between the BTS3202E and the AC surge protection box through the PG connector labeled OUT.
BTS3202E LTE Installation Guide 8 Installing an AC Surge Protection Box and Related Cables Figure 8-20 Securing AC power cables (1) Corrugated pipe (2) Connector between corrugated pipes Step 7 Bind the cables using cable ties at equal spacing of 30 cm (11.81 in.) and verify that the bend radius of the corrugated pipe is not less than 60 mm (2.36 in.). Step 8 Install the PGND cable and equipotential cable, as shown in Figure 8-21.
BTS3202E LTE Installation Guide 8 Installing an AC Surge Protection Box and Related Cables Figure 8-21 Installing the PGND cable and equipotential cable (1) PGND cable (2) Equipotential cable ----End Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 9 Installing Cables 9 Installing Cables About This Chapter This chapter describes the procedure and precautions for installing the PGND cables, power cables, and transmission cables for a BTS3902E in various scenarios. Based on actual requirements, and it also describes how to install an optional monitoring signal cable as required. 9.1 Cabling Requirements Cables must be routed according to the specified cabling requirements to prevent signal interference. 9.
BTS3202E LTE Installation Guide 9 Installing Cables 9.1 Cabling Requirements Cables must be routed according to the specified cabling requirements to prevent signal interference. NOTE If a cable listed below is not required, skip the routing requirements of the cable. General Cabling Requirements The bending radius of the cables must meet the following specifications: l The bending radius of the 7/8'' feeder must be more than 250 mm (9.84 in.
BTS3202E LTE Installation Guide 9 Installing Cables l PGND cables and signal cables must be installed in an untangled and orderly fashion. A certain distance must be reserved between them to prevent interference from each other. l Fuses or switches must not be installed on the PGND cables. l Other devices must not be used for electrical connections of the PGND cables. l All the metal parts in the housing of the equipment must be reliably connected to the ground terminal.
BTS3202E LTE Installation Guide 9 Installing Cables Figure 9-1 Cable connections of a single BTS3202E implementing transmission over an electrical port (1) BTS3202E power cable (2) PGND cable (optional) (4) Fast Ethernet or gigabit Ethernet (5) BTS3202E monitoring signal (FE/GE) cable cable (optional) (3) Equipotential cable (optional) (6) RGPS signal cable (optional) Figure 9-2 shows the cable connections of a single BTS3202E implementing transmission over an optical port.
BTS3202E LTE Installation Guide 9 Installing Cables Figure 9-2 Cable connections of a single BTS3202E implementing transmission over an optical port (1) BTS3202E power cable (2) PGND cable (optional) (3) Equipotential cable (optional) (4) FE/GE fiber optic cable (5) BTS3202E monitoring signal cable (optional) (6) RGPS signal cable (optional) 9.3 Installing a PGND Cable and Equipotential Cable The protection ground (PGND) cable and equipotential cable must be installed based on actual requirements.
BTS3202E LTE Installation Guide 9 Installing Cables Procedure l Install the PGND cable when no AC surge protection box is installed, as shown in Figure 9-3. 1. Connect one end of the BTS3902E PGND terminal to the ground cable on the BTS3902E and the other end to the external ground bar. Figure 9-3 Installing the BTS3902E PGND cable NOTE When installing the PGND cable, tightly press the OT terminal in the correct direction, as shown in Figure 9-4.
BTS3202E LTE Installation Guide 9 Installing Cables 2. l Route the cable by referring to Cabling Requirements, and then use cable ties to bind the cable. 3. Label the installed cable by referring to Attaching a Cable-Tying Label. Install the BTS3902E PGND cable and equipotential cable when an AC surge protection box is installed, as shown in Figure 9-5. 1. Connect one end of the BTS3902E PGND cable to the ground terminal on the BTS3902E and the other end to the AC surge protection box.
BTS3202E LTE Installation Guide 9 Installing Cables 2. Route the cable by referring to Cabling Requirements, and then use cable ties to bind the cable. 3. Label the installed cable by referring to Attaching a Cable-Tying Label. ----End 9.4 Installing a BTS3202E Power Cable A BTS3202E power cable connects the BTS3202E to an external power device, feeding external power into the BTS3202E.
BTS3202E LTE Installation Guide 9 Installing Cables Figure 9-7 Connection of the power cable between the BTS3202E and power equipment l 3. Route the cable by referring to Cabling Requirements, and then use cable ties to bind the cable. 4. Label the installed cable by referring to Attaching a Cable-Tying Label. Install the BTS3202E power cable in the AC power supply scenario when an AC surge protection box is configured, as shown in Figure 9-8. 1.
BTS3202E LTE Installation Guide 9 Installing Cables Figure 9-8 Connection of the BTS3202E power cable to the surge protection box (1) Power cable between the surge protection box (2) Power cable between the BTS3202E and the and external power equipment surge protection box 3. Connect one end of the power cable between the surge protection box and external power equipment to the surge protection box and the other end to external power equipment by referring to 8.
BTS3202E LTE Installation Guide 9 Installing Cables Procedure Step 1 Link the Type N connector at one end of the BTS3202E RF jumper to the ANT port, and connect the other end to an external antenna system, as shown in Figure 9-9. Figure 9-9 Installing the BTS3202E RF jumper Step 2 Wrap the connector of the BTS3202E RF jumper using tape, as shown in Figure 9-10.
BTS3202E LTE Installation Guide 9 Installing Cables NOTE l Before wrapping waterproof tape, stretch the tape evenly until the width of the tape is half of its original width. l Wrap each layer of tape around the connector tightly and neatly, and ensure that each layer of tape overlaps more than 50% of the preceding layer. 1. Wrap each connector with three layers of waterproof tape, from bottom up, then from top down, and finally from bottom up.
BTS3202E LTE Installation Guide 9 Installing Cables tape until all the three layers of the tape are already wrapped. Wrap each layer of tape around the connector tightly. Step 4 Route the cable by referring to Cabling Requirements, and then use cable ties to bind the cable. Step 5 Label the installed cable by referring to Attaching a Sign Plate Label. ----End 9.
BTS3202E LTE Installation Guide 9 Installing Cables Step 3 Install a ground clip on the FE/GE cable by referring to 13.2 Installing a Ground Clip. Step 4 Route the cable by referring to Cabling Requirements, and then use cable ties to bind the cable. Step 5 Label the installed cable by referring to Attaching a Sign Plate Label. ----End 9.6.
BTS3202E LTE Installation Guide 9 Installing Cables Figure 9-14 Installing the FE/GE fiber optic cable Step 4 Tighten the round connector until it snaps shut, as shown in Figure 9-15. Figure 9-15 Tightening the round connector Step 5 Route the cable by referring to Cabling Requirements, and then use cable ties to bind the cable. Step 6 Label the installed cable by referring to Attaching a Sign Plate Label. ----End 9.
BTS3202E LTE Installation Guide 9 Installing Cables Context NOTE The cable route depends on actual requirements. Procedure Step 1 Link the DB15 male connector at one end of the alarm cable to the MON port on the BTS3202E, and then tighten the screw on the connector to 0.25 N·m (2.21 lbf·in.), as shown in Figure 9-16. Figure 9-16 Installing the alarm cable Step 2 Route the cable by referring to Cabling Requirements, and then use cable ties to bind the cable.
BTS3202E LTE Installation Guide 9 Installing Cables Procedure Step 1 Link the DB15 female connector of the RGPS signal cable to the RGPS port on the BTS3202E, and then tighten the screw on the connector until the tightening torque reaches 0.25 N·m, as shown in Figure 9-17. Figure 9-17 Installing the RGPS signal cable Step 2 Route the cable by referring to Cabling Requirements, and then use cable ties to bind the cable. Step 3 Label the installed cable by referring to Attaching a Sign Plate Label.
BTS3202E LTE Installation Guide 10 Installing the Housing 10 Installing the Housing About This Chapter This chapter describes the procedures for installing the upper housing and optional camouflage shell for a BTS3202E after the BTS3202E and related cables are installed. Context If the optional camouflage shell is required, the shell must be installed before the upper housing is installed, and the upper housing must be removed before the shell is removed. 10.
BTS3202E LTE Installation Guide 10 Installing the Housing 10.1 (Optional) Installing a Camouflage Shell This section describes how to install a camouflage shell for a BTS3202E as required. Procedure Step 1 Use an M4 Phillips screwdriver to loosen the two captive screws from the upper housing, as shown in Figure 10-1. Figure 10-1 Loosening the screws from the housing Step 2 Move the upper housing until it is stopped, as shown in Figure 10-2.
BTS3202E LTE Installation Guide 10 Installing the Housing Figure 10-3 Installing the camouflage shell (1) Camouflage shell (2) Slots (3) Tabs Step 4 Use an M4 Phillips screwdriver to tighten the two captive screws to 1.2 N·m, as shown in Figure 10-4. Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 10 Installing the Housing Figure 10-4 Tightening the screws ----End 10.2 Installing the Upper Housing This section describes how to install the upper housing for a BTS3202E. Context NOTE The camouflage shell is optional. Following uses the BTS3202E equipped with a camouflage shell as an example. Procedure Step 1 Close the housing, and use an M4 Phillips screwdriver to tighten the two captive screws to 1.2 N·m, as shown in Figure 10-5.
BTS3202E LTE Installation Guide 10 Installing the Housing Figure 10-5 Closing the housing and tightening the screws ----End Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 11 Checking the BTS3202E Hardware Installation 11 Checking the BTS3202E Hardware Installation This chapter describes how to check the hardware installation after a BTS3202E is installed. Table 11-1 provides the checklist for the BTS3202E hardware installation. Table 11-1 Checklist for the BTS3202E Hardware Installation SN Item 1 The position for each device conforms to the engineering drawing and meets the space requirement.
BTS3202E LTE Installation Guide 11 Checking the BTS3202E Hardware Installation SN Item 11 Labels are correct, legible, and complete at both ends of each cable, feeder, and jumper. Table 11-2 provides the checklist for the installation of an AC surge protection box. Table 11-2 Checklist for the installation of an AC surge protection box SN Item 1 The PG connectors for routing cables on an AC surge protection box are securely installed.
BTS3202E LTE Installation Guide 12 Performing a Power-On Check on the BTS3202E 12 Performing a Power-On Check on the BTS3202E This chapter describes the procedure for performing a power-on check on the BTS3202E. CAUTION After you unpack a BTS3202E, you must power it on within 24 hours. If you power off the BTS3202E for maintenance, you must restore power to it within 24 hours. Figure 12-1 shows the BTS3202E power-on check procedure.
BTS3202E LTE Installation Guide 12 Performing a Power-On Check on the BTS3202E Figure 12-1 BTS3202E power-on check procedure Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 13 Appendix 13 Appendix About This Chapter This section describes the procedure for adding an easy power receptacle (pressfit type) connector.This section describes the procedure for adding OT terminals.This section describes the procedure for adding OT terminals to the surge protection box side of the power cable for the AC surge protection box. 13.
BTS3202E LTE Installation Guide 13 Appendix 13.1 Adding OT Terminals to the Power Cable Connected to the AC Surge Protection Box This section describes the procedure for adding OT terminals to the power cable connected to the AC surge protection box. Context Figure 13-1 shows the cable diagram on labels. Figure 13-1 Cable diagram on labels (1) Cable diagram on labels Procedure Step 1 Cut the cable to the required length based on the actual cable route.
BTS3202E LTE Installation Guide 13 Appendix Figure 13-2 Leading the power cable through corrugated pipes Step 4 Join the corrugated pipes, as shown in Figure 13-3. Figure 13-3 Joining corrugated pipes Step 5 Determine the length of the power cable for different operations based on the labels, as shown in Figure 13-4. Figure 13-4 Determining the length of the power cable Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.
BTS3202E LTE Installation Guide 13 Appendix Step 6 Use a utility knife to strip the specified length of the sheath and shield layer off the power cable, as shown in Figure 13-5. Figure 13-5 Stripping the specified length of the sheath and shield layer Step 7 Strip the sheath off each core wire, as shown in Figure 13-6. Figure 13-6 Stripping the sheath off each core wire Step 8 Add OT terminals to the three core wires, as shown in Figure 13-7. Figure 13-7 Adding OT terminals ----End 13.
BTS3202E LTE Installation Guide 13 Appendix Figure 13-8 Stripping the sheath off the FE/GE cable Step 3 Install the ground clip on the shield layer of the cable, and then use a screwdriver to tighten the screws on the ground clip, as shown in Figure 13-9. Figure 13-9 Tightening the screws on a ground clip (1) Ground cable (2) Ground clip (3) FE/GE cable Step 4 Wrap three layers of waterproof tape and three layers of polyvinyl chloride (PVC) insulation tape at the ground clip.
BTS3202E LTE Installation Guide 13 Appendix Figure 13-10 Wrapping waterproof tape and PVC insulation tape (1) Waterproof tape (2) PVC insulation tape (3) FE/GE cable (4) Ground cable Step 5 Connect the ground cable to an external ground bar. ----End Issue Draft A (2011-07-30) Huawei Proprietary and Confidential Copyright © Huawei Technologies Co., Ltd.