User Manual

Table Of Contents
8. Install drives or drive blanks.
9. Connect the power and data cables.
10. Install the access panel.
11. Slide the server into the rack.
12. Connect each power cord to the server.
13. Connect each power cord to the power source.
14. Power up the server.
The installation is complete.
Riser and riser cage options
Installing primary and secondary risers
Prerequisites
Before installing this option, be sure that you have the following:
The components included with the hardware option kit
T-10 Torx screwdriver
Procedure
1. Power down the server .
2. Do one of the following:
Disconnect each power cord from the power source.
Disconnect each power cord from the server.
3. Do one of the following:
Extend the server from the rack.
Remove the server from the rack.
4. Remove the access panel.
5. Remove the riser cage.
6. Remove the riser board.
84 Riser and riser cage options