Server warnings and cautions
Rack server shipping contents
Tower server shipping contents
Optional installation service
Optimum Environment
Peak server performance depends in part on the environment you select for
installing your server or servers. Select a location that meets standard
environmental requirements for the following:
Space and airflow
Power
Electrical grounding
Temperature
Space and Airflow Requirements
To allow for servicing and adequate airflow, observe the following spatial
requirements when deciding where to install your Compaq, Telco, or
third-party rack:
Leave a minimum clearance of 63.5 cm (25 inches) in front of the rack.
Leave a minimum clearance of 76.2 cm (30 inches) in the back of the
rack.
Leave a minimum clearance of 121.9 cm (48 inches) from the back of
the rack to the rear of another rack or row of racks.
Compaq servers draw in cool air through the front door and expel warm air
through the rear door. Therefore, the front and rear rack doors must be
adequately ventilated to allow ambient room air to enter the cabinet, and the
rear door must be adequately ventilated to allow the warm air to escape from
the cabinet.
IMPORTANT: Do not block the ventilation openings.