User's Manual

Installation 25
5.
Close the main breaker in the House panel on the exterior of the HP POD.
6. Close the remaining breakers in the House panel one by one, following the panel schedule on the
inside of the House panel.
NOTE: If you are installing a high density HP POD, you must also close the main breaker in
the electrical busway 3 panel.
7. Close the main breakers in the electrical busway 1 and electrical busway 2 panels.
8. Inside the HP POD, close the breaker on each drop box that is connected to a rack of IT
components.
9. Power up your remaining racks and IT components following your standard IT startup procedure.
Commissioning the HP POD
Commissioning your HP POD is an optional service and is customized based on your facility. A typical
commissioning process includes the following tests:
Tighten the electrical busway connections
Verify accurate electrical installation
Verify accurate mechanical installation
Test the operation of the BMS and Cooling controls
Test the operation of the smoke detection system
Test the operation of EPO system