Getting Started Guide
Appendix B: Preparing for delivery 32
Item Description Sign-off
7
When installing on an elevated surface, verify that the
maximum height requirements for the circuit breaker actuator
meet the local and national requirements. Verify that proper
landings and the catwalk are planned for electrical cabinet
access.
8
Verify the planning for required egress routes for all HP POD
40c G2 personnel doors, cargo doors, and service area doors,
including landings, the catwalk, and stairs.
9
Verify that the local AHJ is contacted, all applicable codes and
site-specific location guidelines are reviewed, and all required
permits are obtained.
10
Verify that the site location has clearances for the HP POD 40c
G2 installation, including any permanent structures, such as
fences, walls, vestibules, and buildings.
11
Verify that all utilities, overhead and underground, are
identified to maintain required clearance.
12
Verify that there is adequate clearance around the HP POD 40c
G2 for door operation, installation, and maintenance
equipment.
13
Verify that the site location and site pads are marked for any
transformer, external switchboard, generators, and
powerhouses.
14
Verify that the site has provisions for proper grounding and that
the site location includes a grounding electrode system.
15
Verify that the site location has adequate lighting for the HP
POD 40c G2 installation.
16
Verify that a truck and equipment staging areas are identified.
17
Verify the location for the fuel tanks for generators,
powerhouses, and other equipment, if applicable.
18
Verify the locations for cranes off-loading and operation during
HP POD 40c G2 installation.
19
Verify site access and clearances for equipment, including the
crane and forklifts. A clear path to the site must be maintained
with clearance for all gates, headers, utility lines, and so on.
20
Verify that the locations for storage and trash disposal are
identified.
21
Verify that the safety equipment is planned for and in place in
accordance with the customer’s site safety program.
22
Verify the site interfaces and locations to connect the fire alarm,
security system, and communication system to the HP POD 40c
G2. This ensures that the POD can be properly connected to the
site BMS.
23
Verify that proper disposal methods are used for existing or
potentially contaminated and/or hazardous materials.
24
Verify the availability of security systems or equipment,
including site fences, required after construction.
25
Verify the availability of temporary facilities associated with the
relocation of existing services and operations.
26
Verify that all work relating to soil testing, removal, and that site
remediation is complete.
27
Verify that a temporary or permanent load bank is available, if
applicable.