Getting Started Guide
Appendix A: HP site assessment 29
Item Description Sign-off
13. Chilled water
infrastructure
Determine the overall chilled water capacity, available
flow rates, and supply/return temperature restrictions.
Determine if there are any site specific requirements
that mandate additional chilled water equipment, such
as heat exchangers or mixing apparatus. Locate any
existing or planned supply/return headers.
14. Security
Conduct interviews with the customer site engineering
personnel to determine the level of security required for
the HP POD 40c G2 and its infrastructure. The
proposed installation site is assessed for suitability in
relation to the customer requirements.
15.
Recommendations
Following the HP installation site visit, analyze the data
collected and prepare a report of findings. HP must
identify potential obstacles to installation and
recommendations for any additional testing or
changes to the installation plan.
Customer responsibilities
Item Description Sign-off
1. Point of contact
information
Provide HP with the name and telephone number of the
designated point of contact for the purposes of this
service.
2. Service listing
information
Provide all information required under this service listing
or reasonably determined by HP to be necessary to
deliver the service, including but without limitation, any
documentation (internal or external) regarding prior
plans or investigations used to identify the proposed
installation site.
3. Timely
response
Provide a timely response (such as, in a time period that
does not adversely affect the HP scheduled performance
of the service) to all requests for information by HP.
4. Access to
subject areas and
support areas
Provide HP access to all subject areas and support areas,
including the proposed installation site and the
mechanical or electrical infrastructure provided to
support the HP POD 40c G2.
5. Badge access
Provide HP badge access or an escort for the duration of
the site visit to facilitate required access to all necessary
areas.
6. Site
engineering
personnel
Customer site engineering personnel familiar with the
proposed installation site and personnel responsible for
the maintenance and support of the existing infrastructure
must be available to answer questions.
7. Documentation
Provide HP copies of all available mechanical and
electrical system design documentation, including as-built
drawings and electrical single-line drawings. As
appropriate to the specific location, provide HP with
campus maps, building drawings, floor plans, and other
relevant prints to assist in the documentation and
evaluation of the proposed installation site.
8. Network
infrastructure
information
Provide HP information regarding the planned network
infrastructure connection points and pathways.