Preparing for delivery and assembly 12
Preparing for delivery and assembly
Shipping considerations
The HP POD 240a is packaged for shipping such that exposure to weather does not result in damage
to the components.
The HP POD 240a is shipped on air-ride trailers to avoid vibrations during shipment.
The HP POD 240a components are shipped based on the assembly plan and available space at the
customer site.
Depending on the site location, additional restrictions and permits might be required, which can effect
the delivery time line.
Suggested assembly installation equipment
Crane (2)
Forklift (1)
Scissor lift (2)
Boom lift (1)
Temporary flood light towers (2)
Fuel spill containment kit
Portable generator
Safety for assembly
National, state, regional, and local safety regulations must be enforced at all times to prevent work-related
injuries. Before installation, HP recommends reviewing the following OSHA safety sections:
Equipment safety—Crane, forklift, scissor-lift, boom-lift, and tools
Traffic safety
Assembly and personnel safety
Electrical safety
Fuel spill containment safety
PPE and head protection
All contractors must adhere to OSHA requirements for the use of PPE to reduce employee exposure to
hazards. The construction area around the HP POD 240a construction site is a required hard-hat area, and
all personnel who enters the construction site must wear a hard hat, safety vest, and any additional OSHA,
HP, and customer required PPE.