Getting Started Guide
Appendix B: Preparing for delivery 30
Item Description Sign-off
1
Verify that the HP POD 240e NA is not in a drainage path or
flood prone area to prevent water from entering the HP POD
240e NA. HP recommends setting the HP POD 240e NA on a
raised site pad.
2
Verify that the water quality meets drinking water standards.
Adiabatic media water supply
Item Description Sign-off
1
Verify that the water pressure is between 20-70 psi (138-483
kPa) and that water temperature is between 1°C to 30°C
(34°F to 86°F).
2
Verify that the water instant flow-rate is no lower than the rated
flow of the fill solenoid valve (1.5 gpm maximum flow per
adiabatic unit, maximum instantaneous.)
3
Verify that water hardness is no greater than 40degFH or
equal to 400 ppm of CaCO3.
4
Verify that demineralized water (preferred) or drinking
(potable) water is used.
Power requirements
Item Description Sign-off
1
Verify that the following requirements are complete:
•
Short circuit analysis
•
Arc flash study
•
Circuit breaker coordination studies
2
Verify that the power installation work is completed according
to the approved conduit routing drawings that show the exact
routes, plan view, sections, and elevations.
3
Verify that temporary site power for installation and
construction is planned and available.
4
Verify adequate site power (on page 13) per HP POD 240e
NA requirements.
General
Item Description Sign-off
1
Verify the utility connection including the main utility
transformers and metering equipment.
2
Verify the third-party commissioning services that might be
required by the owner.
3
Verify that the HP Project Team activities are coordinated with
other site construction activities.