User's Manual

NOTE: When a mixed configuration of BL860c i4, BL870c i4, and BL890c i4 server blades and
other c-Class server blades are in the same enclosure, the preferred location for the P711m cards
is slot 3.
Use the procedure for installing standard mezzanine cards to install the SAS controller board, see
“Mezzanine cards” (page 49) for more information.
Installing the Supercap Pack
The Supercap Pack snaps onto the mounting bracket to secure the Supercap Pack inside the server
blade.
NOTE: The mounting bracket is installed either on top of a mezzanine card in slot 1, or the
mezzanine blank in slot 1, depending upon the customer's configuration. If no card is used in slot
1, the mezzanine card blank must be installed for the bracket to clip onto.
NOTE: The Supercap Pack includes two plastic tabs that must be removed for proper fit in the
BL860c i4, BL870c i4, and BL890c i4 server blades. One tab is located on the rounded end of
the Supercap Pack, the other tab is directly above the cable as it exits the plastic housing of the
Supercap Pack. To remove these tabs, squeeze them firmly toward each other (significant force is
required). Optionally, these two tabs can be clipped off even with the rest of the Supercap Pack.
1. Position the Supercap Pack with the print side down and push the end of the cable that is
connected to the Supercap Pack under the mounting bracket’s C-hook, routing the cable so
its supercap end is on the side of the hook that is away from slot 3
2. Push the other end of the Supercap Pack down between the two restraining clips.
3. Consolidate and secure remaining cable length using tie wrap or similar retention method.
Installing internal components 53