Technical information
188
Country-Specific Considerations: Japan
1. Device to Rack PDU power cable
IEC C13 to C14, 10/15a cable
typical: P/N 36L8886 (2.8m)
requirement: C14 plug, long enough to reach
available option: 94G7448 (14ft)
2. Rack PDU to wall line cord
IEC C19 to country-specific connector,
16/20a, 14ft (4.3m)
3. Rack PDU to UPS power cable
IEC C19 to C20, 16/20a
P/N 00N7700 (2m)
provided with P/N 37L6861 (APC SU-5000RMB)
4. Rack PDU to Front-end PDU power cable
IEC C19 to C20, 16/20a
P/N 00N7698 (1m)
provided with the Front-end PDUs
5. Front-end PDU to wall line cord
special to country-specific connector, 30/32a,
8.2ft (2.5m)
Power Cables:
(2) Line Cords: Rack PDUs
(5) Line Cords: Front-end PDUs
Part
Number
Plug Type
Source Circuit (single
phase 50/60Hz)
PDU Output
(single phase 50/60Hz)
37L6866
NEMA L5-20P 100Vac, 20a seven 100Vac, shared 15a
NEMA L6-20P 200Vac, 20a seven 200Vac, shared 15a
Part
Number
Plug Type
Source Circuit (50/
60Hz)
PDU Output
(single phase 50/60Hz)
37L6883 NEMA L5-30P 100-127Vac, 30a, single-phase
three 100-127Vac, 20a each, shared
30a
37L6884 NEMA L6-30P
200-240Vac, 30a, single phase
line-to-line with ground
three 200-240Vac, shared 20a
37L6886 NEMA L21-30P
200-250Vac, 30a, three-phase
Y-connection with neutral
three 100-127Vac (115-145), 20a
each
37L6885 IEC 309-2P+Gnd 220-240Vac, 32a, single-phase
three 220-240Vac, 16a each,
shared 32a
37L6887 IEC 309-3P+N+Gnd
380-415Vac, 32a, three-phase
Y-connection with neutral
three 220-240Vac, 16a each
C
3000W
C
1300W
C
1300W
C
1300W
C
11 5 0 W
C
11 5 0 W
C
11 5 0 W
W
W
200V
1 phase
20a
200V
3 phase
w/neutral
30a
200V
1 phase
30a
L6-30P
L6-20P
L21-30P
200V
shared 20a
4000W
3450W
11 5 V
High Voltage
NOTE:
C = Rack PDU has a 15a circuit breaker
W = FE PDU has a 20a fuse
Power Load Capacity -- xSeries / Netfinity Rack Systems
C
1500W
100V
1 phase
20a
L5-20P
Low Voltage