Backing up and Restoring HP Insight Management 7.0 Central Management Server (Windows)
53
During the second phase of the VCEM section, mxsync issues requests to VCEM to
resynchronize each VC domain managed by VCEM.
Note:
During the analysis step of phase 2, mxsync displays an ISSUE for
each VC Domain managed by VCEM stating that the VC Domain
MAY need to be synchronized with VCEM. This is only a potential
issue. The test to check if the VC Domain is out of sync temporarily
places the VC Domain in maintenance mode and therefore can
only be performed during the execution step.
Note:
If VC modules were added to or removed from a VC Domain as a
post-backup activity, the Domain Synchronization step will fail.
Additional manual synchronization steps will have time be
performed at this time in order to pass this phase of mxsync. See
Appendix E: VCEM resynchronization actions
for more details.
**** Analysis: Domain synchronization ****
**** Section 2 of 5, phase 2 of 2 ****
Synchronize the state of VCEM with the defined VC Domains.
Synchronize VC Domain STR00140_vc_domain in VCEM.....................[ACTION]
ISSUE: VCEM may be out of sync with the VC Domain.
RESOLUTION: The VC Domain will be checked and, if necessary,
synchronized in VCEM.
Analysis summary:
1 check performed
1 action needed
0 actions require input
0 advisories
0 errors
Mark VC profile VCS101_12744828a5d addresses external:
50:01:43:80:02:A3:00:2B, 50:01:43:80:02:A3:00:2A,
50:01:43:80:02:A3:00:2D, 50:01:43:80:02:A3:00:2C,
00-21-5A-9B-00-04, 00-21-5A-9B-00-06, 00-21-5A-9B-00-05,
00-21-5A-9B-00-07.......................................................[OK]
Mark VC profile VCS301_134f1bf0233 addresses external:
50:01:43:80:02:A3:00:15, 50:01:43:80:02:A3:00:14,
50:01:43:80:02:A3:00:2F, 50:01:43:80:02:A3:00:2E,
00-21-5A-9B-00-0E, 00-21-5A-9B-00-1C, 00-21-5A-9B-00-0F,
00-21-5A-9B-00-1D........................................................[OK]
Execution summary:
10 actions performed
0 advisories