HP StorageWorks XP24000 Disk Array Site Preparation Guide, v01 (AE131-96002, June 2007)
ReferenceNoYesChecklist questions
“Vibration specifications” on page 35
“Acoustics” on page 36
Does the computer room support other
environmental considerations (such as vibration
and acoustics)?
“Electrical requirements” on page 42Are two AC outlets, on different lines, available
for the equipment?
“Line voltage” on page 42
“AC line voltage requirements” on page 47
Does the input voltage correspond to the DKC
and DKU equipment specifications?
“Branch circuit breakers” on page 42Are the input circuit breakers adequate for
equipment loads?
“Frequency” on page 42Does the input frequency correspond to
equipment specifications?
“UPS” on page 45Is an appropriate uninterruptible power supply
(UPS) strategy in place?
“Sources of electrical interference” on page 45If lightning arresters are recommended, are they
installed?
“Sources of electrical interference” on page 45Have all sources of electrical interferences been
corrected?
NADoes the customer site have access control (for
example, will HP representatives need an
escort)?
NADoes the computer room have access control
(for example, will HP representatives need a
security code)?
“Delivery space requirements” on page 22Are all floors, stairs, elevators, stairwalkers, lifts,
ramps, or ladders needed to move the
equipment adequate to support its weight and
size?
“Delivery space requirements” on page 22Will the equipment fit through all doors and
corridors and in lifts?
NADoes the building have a loading dock?
Maximum access height is _____m.
NAFor any additional equipment required (for
example, connectors, receptacles, cables, and
any equipment not supplied by HP), is the
equipment on site and ready for use?
Site prep time allowances
The following site prep tasks may require several weeks:
• Acquiring required power connectors
• Arranging for an electrician
• Adding or modifying air conditioning systems
Site prep team and tasks for the HP XP24000 Disk Array16