HP XP P9500 Site Preparation Guide (AV400-96609, January 2014)

Figure 12 Service clearances for a six rack system
*1 Clearance (a+b) is based on the floor load rating and the clearance (c). Floor load rating and
required clearances are shown in Table 22 (page 35).
*2 Clearance (d) is required over 300mm to open the front door. In the case that the clearance
(d) is less tan the clearance (a), give priority to clearance (a).
Table 22 Floor load rating and required clearances for a six rack configuration
Required Clearance (a+b) mFloor Load
Rating
Clearance (c) m
(kg/m2)
C=0.6C=0.6C=0.4C=0.2C=0
00000.1500
000.10.40.7450
0 .10.50.81.11.5400
0.91.41.82.22.6350
Service clearance, floor cutout, and floor load rating 35