Veritas Storage Foundation for Oracle 5.0 Graphical User Interface Guide, HP-UX 11i v3, First Edition, May 2008

7
In the Create Snapshot Database page, set Oracle home.
8
Enter the target database information:
New Oracle SID
Relocate path
9
Click Next to set the schedule parameters.
See “Set the schedule parameters for an automated task” on page 106.
Set the schedule parameters for an automated task
Specific routine
Week days
Days of the month
Specific dates
The scheduler enables you to set or modify schedule parameters for automated
tasks based on:
To set schedule parameters
1
Select and configure a task.
See To create a database checkpoint” on page 104.
See To create a database snapshot” on page 104.
See To clone a database using checkpoint” on page 105.
See To clone a database using snapshot” on page 105.
After you configure the task, you must set the schedule parameters.
2
To set a specific routine, click Specific Routine and set the parameters as
required:
Start time
End time
Date for scheduled effects
Restart task option for run day
Days before repeating task
Start date
3
To set weeks days, click Week Days and check the days you want the
automated task to run.
Automating database tasks
Set the schedule parameters for an automated task
106