HP SureStore E Disk Array XP512 Site Prep Guide
The Site Prep Team and Tasks
15
Electrical Yes No Reference
áwhen completed
q Are two AC outlets/DKU (on different lines) available for the
proposed equipment?
qqpage 44
q Does the input voltage correspond to equipment specifications? qqpage 41
q Are the input circuit breakers adequate for equipment loads? qqpage 41
q Does the input frequency correspond to equipment specifications? qqpage 42
q Are lightening arresters installed? qqpage 47
q Has all sources of electrical interferences been corrected? qqpage 47
Air-Conditioning Yes No Reference
á when completed
q
Can the temperature be maintained between 20
o
- 30
o
C?
qqpage 61
q
Can temperature changes be held to less that 5
o
per hour?
qqpage 61
q Can humidity level be maintained between 40% and 60%? qqpage 61
Building Access and Security Yes No Reference
á when completed
q Is there access control to the computer room? qqpage 67
q Is there access control for the customer site? qqpage 67
q Will any stair-walkers, lifts, ramps, floor coverings, or ladders be
required to install the equipment?
Define: _____________
qqpage 67
q Will the equipment fit through all doors, corridors, and in lifts, both
in size and weight?
qqpage 21
q Does the building have a loading dock?
Maximum access height is _____m.
qqpage 67