HP StorageWorks XP12000 Disk Array Site Preparation Guide (AE002-96040, March 2008)
ReferenceNoYesCheck items*
Mechanical vibration
specifications, page 38
Acoustic specifications, page 39
Does the computer room support other
environmental considerations (such as
vibration and acoustics)?
*
Electrical requirements, page 42
Are two AC outlets, on different lines,
available for the equipment?
*
Line voltage, page 43
AC line voltage requirements, page
49
Does the input voltage correspond to
the DKC and DKU equipment
specifications?
*
Branch circuit breakers, page 43
Are the input circuit breakers adequate
for equipment loads?
*
Frequency, page 43
Does the input frequency correspond to
equipment specifications?
*
Uninterruptible power supply
(UPS), page 46
Is an appropriate uninterruptible power
supply (UPS) strategy in place?
Sources of electrical
interference, page 46
If lightning arresters are recommended,
are they installed?
Sources of electrical
interference, page 46
Have all sources of electrical
interferences been corrected?
*
NA
Does the customer site have access
control (for example, will HP
representatives need an escort)?
NA
Does the computer room have access
control (for example, will HP
representatives need a security code)?
Delivery space requirements, page 47
Are all floors, stairs, elevators,
stairwalkers, lifts, ramps, or ladders
needed to move the equipment
adequate to support its weight and size?
*
Delivery space requirements, page 47
Will the equipment fit through all doors
and corridors and in lifts?
*
NA
Does the building have a loading dock?
Maximum access height is _____m.
*
NA
For any additional equipment required
(for example, connectors, receptacles,
cables, and any equipment not supplied
by HP), is the equipment on site and
ready for use?
Site preparation time allowances
The following site preparation tasks may require several weeks:
• Acquiring required power connectors
Site preparation team and tasks16