HP StorageWorks XP10000 Disk Array Site Preparation Guide (AE102-96014, March 2008)

ReferenceNoYesCheck items*
Electrical requirements, page 37
Are sufficient AC outlets, on different
lines, available for the equipment?
*
Electrical requirements, page 37
Does the input voltage correspond to
the equipment specifications?
*
Electrical requirements, page 37
Are the input circuit breakers adequate
for equipment loads?
*
Electrical requirements, page 37
Does the input frequency correspond to
equipment specifications?
*
Uninterruptible power supply
(UPS), page 39
Is an appropriate uninterruptible power
supply (UPS) strategy in place?
Protection against sources of electrical
interference, page 39
If lightning arresters are recommended,
are they installed?
Protection against sources of electrical
interference, page 39
Have all sources of electrical
interference been corrected?
*
N/A
Does the customer site have access
control (for example, do HP
representatives need an escort)?
N/A
Does the computer room have access
control (for example, do HP
representatives need a security code)?
Dimensions and weights, page 19
Are all floors, stairs, elevators,
stairwalkers, lifts, ramps, or ladders
needed to move the equipment
adequate to support its weight and size?
*
Dimensions and weights, page 19
Will the equipment fit through all doors
and corridors and in lifts?
*
Dimensions and weights, page 19
Does the building have a loading dock?
Maximum access height is _____m.
*
N/AAdditional equipment
N/A
For any additional equipment required
(for example, connectors, receptacles,
cables, and any equipment not supplied
by HP), is the equipment on site and
ready for use?
Site preparation time allowances
The following site preparation tasks may require several weeks:
Acquiring required power connectors
Arranging for an electrician
Adding or modifying air conditioning systems
Making building alterations
Site preparation team and tasks14