Compaq StorageWorks Data Replication Manager HSG80 ACS Version 8.5P Operations Guide
4–22 Compaq StorageWorks Data Replication Manager HSG80 ACS Version 8.5P Operations Guide
Configure the Controllers at the Initiator Site
Pre-Configure Procedure
Prior to configuring the controllers at the initiator site, be sure to follow these preparatory
steps:
■ Identify the worldwide name on the host bus adapters.
■ Establish the name that you will assign to the initiator site. This name should be
different from the one you assigned to the target.
Controller Configuration Procedure
The first step to getting your DT system up and running involves setting up and
configuring the controllers. These tasks are outlined below:
1. Ensure that all BA370 enclosures, Fibre Channel switches, Power Distribution Units
(PDUs), and the main power supply are off.
2. Plug all cabinet PDU power cords into the main power receptacles.
3. Be sure that you have a serial connection to each of the controllers.
4. Apply power to the main power source.
5. Turn on all PDUs.
6. Ensure that the switches are powered on but not cabled.
NOTE: When the BA370 cabinets are turned on, the controllers will boot if the PCMCIA cards are
already installed. If there are no cards in the controller slots, insert them now, and depress the
reset button. Refer to the HSG80 Array Controller ACS Version 8.5 Configuration Guide, for
complete instructions on how to properly seat the controller cards.
7. Turn on the BA370 cabinets.
8. Establish a local connection to the controller. Refer to the HSG80 Array Controller
ACS Version 8.5 Maintenance and Service Guide for instructions.
9. Verify that all controllers are on and functional by looking for the CLI prompt on the
maintenance port terminal.
NOTE: Unless otherwise noted, all operations may be conducted from controller A.
10. Issue the following CLI command:
SHOW THIS_CONTROLLER