Maintenance Analysis Procedures
3-13
Maintenence Analysis Procedures
Was the maintenance action successful?
NO YES
The product is operational. Exit MAP.
6
Verify power supply operation.
a. Inspect each power supply to determine if the amber failure LED
is illuminated.
b. If an amber LED is illuminated, ensure the indicated power
supply is correctly installed and seated. Partially remove and
reseat the power supply. Refer to RRP 2: Redundant Power
Supply.
Was the maintenance action successful?
NO YES
The product is operational. Exit MAP.
A power supply failure is indicated. Go to step 3.
MAP 0200: POST Failure Analysis
This MAP describes fault isolation for a POST failure. The failure
indicator is event code 400 or 411 observed at the Event Log (EFCM
Basic Edition or Element Manager interface).
1
Ta bl e 3 -5 lists event codes, explanations, and MAP steps.
Table 3-5 MAP 200 Event Codes
Event
Code
Explanation Action
400 Power-up diagnostic failure. Go to step 2.
411 Firmware fault. Go to step 4.