FW 07.00.00/HAFM SW 08.06.00 McDATA Sphereon 4500 Fabric Switch Installation and Service Manual (620-000159-320, April 2005)
4-56
McDATA Sphereon 4500 Fabric Switch Installation and Service Manual
— The green LED associated with the Ethernet port blinks
momentarily while the port is tested.
— The blue/green and amber LEDs associated with the ports
blink momentarily while the ports are tested.
4. After successful POST completion, the green power (PWR) LED
remains illuminated and all amber LEDs extinguish.
5. If a POST error or other malfunction occurs, go to MAP 0000: Start
MAP on page 3-6 to isolate the problem.
Power-Off Procedure
To power off the switch:
1. Notify the customer the switch is to be powered off. Ensure the
customer’s system administrator quiesces Fibre Channel frame
traffic through the switch and sets attached FC-AL devices
offline.
2. Set the switch offline. For instructions, refer to Set the Switch
Online or Offline on page 4-48.
3. Disconnect power cord(s) from the power supply AC connectors
at the rear of the switch.
IML, IPL, or Reset the Switch
This section describes procedures to IML, IPL, or reset the Sphereon
4500 Switch. An IML or reset is performed at the switch front panel
using the IML/RESET button. An IPL is performed from the
management server (Element Manager application). The SANpilot
interface does not provide an IML, IPL, or switch reset function.
ATTENTION ! A reset should only be performed if a CTP card failure is
indicated. Do not reset a managed product unless directed to do so by a