HP StorageWorks XP24000 Continuous Access Software User and Reference Guide, v01 (T5278-96002, June 2007)

1. Allow direct control of the host impact metrics using a methodology called Load Balancing. Load
balancing allows management of the thresholds for inducing host delay and for the degree of
induced delay.
2. Use Business Copy to provide a tertiary Point-in-Time (PiT) copy in support of the DR/BC
requirements. The PiT copy may be manually controlled at specied times or be automated on a
continuing interval b asis using HP NanoCopy. With this practice, the induced host delay may
be
minimize d, and in some cases removed, without impacting a DR/BC solution. This solution
allows the tertiary copy to be used for testing and/or backup.
3. Use Continuous Access Asynchronous as a data replication application only. All induced delay
may be removed at user discretion, and the DR/BC solution will remain usable as long as the
sustained write update rate and the ability of the n etwork to service the write updates does not
over-commit the availability of cache/sidele. Suspension of the remote copy environment in this
conguration is probable dependent upon write update demand a nd network capability.
144
Continuous Access Load Balancing and Sidele Management and Control