3.5.1 Matrix Server Upgrade Guide
Copyright © 1999-2006 PolyServe, Inc. All rights reserved. 21
3
Double Rolling Upgrades
This chapter describes how to upgrade Matrix Server on clusters that
meet these conditions:
• The nodes have 64-bit CPUs and are currently running in 32-bit mode,
but will upgrade to 64-bit mode.
• The nodes are currently running Matrix Server 3.1.2.
The rolling upgrade does not require any matrix downtime. Each server
is removed from the matrix, upgraded, and then returned to the matrix.
Rolling Upgrade Considerations
You should be aware of the following when upgrading to the Matrix
Server 3.5.1 release.
Order for Upgrading Servers
Servers must be upgraded one-at-a-time during the upgrade. The server
with the numerically highest primary IP address must be upgraded
first. Then continue to upgrade the servers in descending order of IP
address, with the server with the lowest primary IP address being
upgraded last.
If you have two networks and the IP addresses are ordered differently on
each network, you will need to determine the IP addresses by which the
servers are known to the matrix and then use those addresses to
determine the order for the upgrade.