Site Preparation Guide, Third Edition - HP 9000 rp7420 Server

Chapter 2
General Site Preparation Guidelines
Sample Site Inspection Checklist
41
24. Is there a fire protection system in the
computer room?
25. Is antistatic flooring installed?
26. Are there any equipment servicing hazards
(loose ground wires, poor lighting, and so on.)?
Cooling
No. Area or condition Yes No
27. Can cooling be maintained between 5°C and
35°C (up to 5000 ft.)? Derate 1 °C/1000 ft. above
5000 ft. and up to 10,000 ft.
28. Can temperature changes be held to 5 °C per
hour with tape media? Can temperature
changes be held to 20 °C per hour without tape
media?
29. Can humidity level be maintained at 40% to
55% at 35 °C noncondensing?
30. Are air conditioning filters installed and clean?
Storage
No. Area or condition Yes No
31. Are cabinets available for tape and disc media?
32. Is shelving available for documentation?
Training
No. Area or Condition
33 Are personnel enrolled in the System
Administrator’s Course?
34 Is on-site training required?
Table 2-6 Site Inspection Checklist (Continued)
Please check either Yes or No. If No, include comment or date
Comment
or Date