Installing the server into the rack
Loading the server into the rack rails
Attaching the cable management arm
Reinstalling the power supplies
Securing the server in the rack for shipping
Connecting the AC power cord and peripheral devices
Securing cables with the cable management arm
Powering up the server
Installing an operating system
Registering the server
Routine maintenance
The chapter concludes with routine maintenance guidelines and resources. For
additional information, visit the website:
www.hp.com/servers/proliant/manage
Server Installation Overview
Installing the server in the rack requires the following actions:
1. Select an appropriate site for the server based on the environmental and stability
requirements discussed in Chapter 2, Planning the Server Installation.
2. Unpack the server and locate the rack-mounting hardware described in the
Server Shipping Contents section of Chapter 2, Planning the Server
Installation.
3. Install any expansion boards or hardware options such as memory. To install the
major hardware items, refer to Chapter 3, Installing Hardware Options or
follow the installation instructions provided in each hardware option kit.
4. To minimize server weight, remove the hot-plug power supplies and do not
install hot-plug hard drives until the server is mounted in the rack. Refer to
Removing the Power Supplies in this chapter.