4.6.3 Cable Management Procedure
Cable management procedure will depend on the rail solution used for an installation.
4.6.3.1 Fixed-Rail Cable Management
For details on the installation procedures in this section, refer to the Compaq ProLiant DL360
Setup and Installation Guide.
Figure 4-23 shows how the power cord and other peripheral/network cables from the server rear
panel connectors are routed into the cable tray clamp. Figure 4-24 shows how to bundle the
cables together for fixed rail installations. The cable bundles should be routed vertically through
the cable D-rings attached on the rack frame.
Figure 4-23. Cable tray clamps securing step on a fixed rail cable tray
Figure 4-24. Cable bundle grouping for fixed rail installation