The Optimum Environment
When installing your Compaq ProLiant DL320 server in a rack, select a
location that meets the environmental standards described in the following
paragraphs.
Space Requirements
Consider the following spatial requirements when deciding where to install
your rack:
Leave a minimum clearance of 25 inches in front of the rack to allow the
front door to open all the way and to allow for adequate airflow.
Leave a minimum clearance of 30 inches in the back of the rack to allow
for servicing and adequate airflow.
Power Requirements
WARNING: To reduce the risk of personal injury, fire, or damage to the
equipment, do not overload the AC supply branch circuit that provides power to
the rack. Consult the electrical authority having jurisdiction over your facility’s
wiring and installation requirements.
The installation of this equipment shall be in accordance with local/regional
electrical regulations governing the installation of information technology
equipment by licensed electricians. This equipment is designed to operate in
installations covered by NFPA 70-1999 (National Electric Code) and
NFPA-75, 1992 (code for Protection of Electronic Computer/Data Processing
Equipment). For electrical power ratings on options, refer to the product’s
rating label or the user documentation supplied with that option.
When installing more than one server, you may need to use additional power
distribution devices to safely provide power to all devices.
The power load must be balanced between available AC supply branch
circuits.
The overall system AC current load must not exceed 80 percent of the
branch circuit AC current rating.