Site Preparation Guide, Fifth Edition - HP Integrity Superdome and HP 9000 Superdome
Chapter 6
Pre-Installation Survey
Typical Installation Schedule
65
Typical Installation Schedule
The following schedule lists the sequence of events for a typical system installation:
• 60 days before installation
— Floor plan design completed and mailed to Hewlett-Packard
• 30 days before installation
— Primary power and air conditioning installation completed
— Telephone and data cables installed
— Fire protection equipment installed
— Major facility changes completed
— Special delivery requirements defined
— Site inspection survey completed
— Delivery survey completed
— Signed copy of the site inspection and delivery survey mailed to Hewlett-Packard
— Site inspection and pre-delivery coordination meeting arranged with a Hewlett-Packard
representative to review the inspection checklist and arrange an installation schedule.
• 7 days before installation
— Final check made with a Hewlett-Packard customer engineer to resolve any last-minute problems










