HP StorageWorks Enterprise Virtual Array 3000/5000 updating product software guide (VCS 3.110) (5697-7959, February 2009)
2 Pre-upgrade tasks
There are a number of necessary tasks that can be performed prior to beginning the upgrade. Performing
these tasks prior to, rather than during, the upgrade minimizes the time required to perform the VCS
upgrade procedure.
The required tasks differ depending on your system configuration. They focus on upgrading components
to ensure they meet the supported c on figuration for VCS 3.110. Table 3 provides a checklist so you can
track your progress as you perform these pre-upgrade tasks.
If you’re in a supported configuration running VCS 3.028, the majority of these tasks are considered
optional.
Table 3 VCS 3.110 Pre-upgrade task checklist
Checking current software versions,page19
Time required: 10–15 minutes
When to perform: Any time prior to the upgrade
Check vers
ions of all applicable installed management software.
Checking the storage system hardware (Optional),page22
Time required: 15– 2 0 m i n u t es
When to perform: 1–2 weeks prior to the upgrade. Provide enough time to order and replace any failed
components.
Check hardware status using HP Command View EVA.
Check hardware components in the Unmappable Hardware folder.
Replace hardware as needed.
Checking and upgrading your SAN infrastructure (Optional), page 24
Time required: Varies depending on how many ha rdware and software components require replacement
or upgrade
When to perform: Any time prior to the upgrade
Things you will need:
• Connectivity release notes. See “Required documentation” on page 14.
• SAN Visibility tool. See “Collecting SAN configuration data using SAN Visibility (Optional)”onpage24.
VerifyallhostHBAsanddriversaresupported.
Verify Fibre Channel switch firmware is supported.
Upgrade unsupported components as necessary.
Selecting an appropriate time to perform an online upgrade, page 29
Time requ
ired: Varies depending on how long it will take to gather I/O data
When to perform: Any time prior to the upgrade
Run HP Co
mmand View EVAPerf to gather I/O data.
Analyze data to identify a time period that meets the I/O criteria.
Managing host I/O timeouts for an online upgrade, page 33
Time required: Varies depending on number of hosts
When to perform: Any time prior to the upgrade
Determine if any host LUN timeouts have been changed from their defaults.
Reset any changed LUN timeout parameters to a minimum of 60 seconds.
HP StorageWorks Enterprise Virtual Array 3000/5000 updating product software guide (VCS 3.110)