HP StorageWorks 3000/5000 Enterprise Virtual Array updating product software guide (VCS 3.110) (5697-8108, March 2009)
7. Click Next Step.
The new storage system software is copied to the controllers and validated. A progress page
opens and is updated as the code segments are validated. For a description of each code
segment, see Table 6 on page 46.
When the code validation is complete, the Code Load Storage System-Page 3 window opens.
Figure 20 Validating code segments complete
Table 6 System software code segment descriptions
DescriptionSegment
Text file with information about the new code and upgrade requirements. Displayed
by HP Command View EVA and not sent to the controller.
Before text
File stored on the controller's card describing contents of this superfile.Information file
Firmware for the Operator Controler Panel (LCD entry and display panel) PIC (8-
bit) processor chip.
OCP image
Firmware for System Data Center (Battery, Temperature and Blower manager) PIC
(8-bit) processor chip.
SDC image
Firmware for the GLUE chip FPGA, stored in EEPROM.Glue image
Firmware for the CanBus Interface Chip (drive shelf out-of-band communications
chip) PIC (8-bit) processor chip.
CBIC image
File enabling HP Command View EVA to translate binary event data to text. Not
sent to the controller.
Event text file
Firmware for the Drive Shelf Environmental Monitoring Unit (EMU) module. Stored
on the controllers program card and contains the image for the CTS I/O module.
EMU image
Initial Firmware that the controller's main processor (PPC) runs after reset or power-
on.
Boot image
Upgrading the Enterprise Virtual Array46