HP V142 Rack Options Installation Guide

About this guide 5
KeyboardThe rack keyboard requires installation of a 1U keyboard drawer rack option kit.
MonitorThe monitor requires installation of a monitor/utility shelf rack option kit unless you are
using a rack-mountable flat-panel monitor.
Server console switchIf a console switch is configured, use the CPU-to-console switch cable
included with the server. The standard distance between the console switch and the keyboard,
monitor, and mouse can vary by 3-, 7-, 12-, 20-, and 40-ft lengths.
NOTE: National electrical regulations governing the installation of building wiring require
that an appropriate cable, meeting fire-safety standards, must be used any time cabling is
routed:
Through an overhead drop-ceiling
Under raised flooring
From room to room
From floor to floor
Be sure that the cable jacket or sleeving is made of material that does not burn easily and
does not exude toxic fumes when exposed to heat. Be sure that the cable you have selected is
appropriate for your installation site. If you require a U.S. plenum-rated (CL2P) cable, contact
your local HP authorized reseller to obtain any of the following options:
149363-B21-20-foot plenum cable
149364-B21-40-foot plenum cable
Rack baying option kitsThe number of baying kits needed to join a series of racks is one less than
the number of racks in the suite. Each baying kit supplies parts to bay two cabinets on 600 mm (24
in) center line spacing.
Side panelsOnly one set of side panels is required for each row of bayed racks.
Stabilizer kitA stabilizer kit is either required or recommended, depending on your rack
configuration.
o Rack rows with four or more bayed together racks do not need a stabilizer installed.
o Single racks or bays of less than four connected racks, must have a stabilizer installed.